PLS与福蒂斯丘(Fortescue)签署20年购电协议,为Pilgangoora锂矿供电

First-of-its kind Pilbara power play brings Fortescue and PLS together

Public on this site

AI summary

PLS子公司Pilgangoora Operation与福蒂斯丘(Fortescue)子公司FMG Clean Energy签署20年购电协议,每年至少获得325吉瓦时电力,用于西澳Pilgangoora项目在P2000运营模式下的用电需求。PLS预计单位运营成本较P2000扩建10年平均估算降低约15–20美元/吨,并计划在2026–27至2028–29财年投入约1.5亿美元建设输电连接和电力设施,目标2029年开始供电。项目将通过约25公里新建220千伏输电线路接入福蒂斯丘的Turner River太阳能农场,PLS出资并拥有其中约20公里,电网容量超过100兆瓦。

Text · original

The Chinese translation is being made; the original is shown for now.

查看配图
Image: agnormark/adobe.stock.com

PLS has secured a minimum of 325 gigawatt-hours per annum of electricity for its Pilgangoora operation in Western Australia, supporting the project’s forecast power demand under the P2000 operating model.

This comes after PLS subsidiary Pilgangoora Operation executed a 20-year power purchase agreement (PPA) with Fortescue subsidiary FMG Clean Energy.

According to PLS, this PPA underpins its Pilgangoora power strategy in delivering a materially lower cost of power, enhanced long-term energy security, capacity for future growth and a substantially higher share of renewable energy in the site’s power mix.

“We are pleased to partner with Fortescue and become their first external Green Grid customer,” PLS managing director and chief executive officer (CEO) Dale Henderson said.

“We commend Fortescue’s leadership in bringing its vision for large-scale, lower-emissions power infrastructure across the Pilbara to life, and strongly support the opportunity for shared infrastructure to benefit industry across the region.”

Under the agreement, PLS expects to reduce its forecast unit operating costs by approximately $15–20 per tonne compared with the recently approved P2000 expansion’s 10-year average operating cost estimates.

The company said it will invest approximately $150 million in transmission connections and power infrastructure between the 2026–27 and 2028–29 financial years, with electricity supply targeted to commence in 2029.

The project will connect Pilgangoora to Fortescue’s Turner River solar farm through approximately 25km of new 220-kilovolt transmission infrastructure, with PLS funding and owning around 20km of the connection.

The network will have capacity exceeding 100 megawatts, accommodating potential future developments such as underground mining and fleet electrification.

“This agreement further strengthens our low-cost position at Pilgangoora, improving our competitiveness and resilience through lithium market cycles,” Henderson said.

“Access to lower-cost, lower-emissions power will deliver further improvements to the economics of our recently approved P2000 Project expansion, beyond those announced at FID, while providing capacity to support future growth.”

Fortescue chief executive officer Dino Otranto said the agreement represented an important step in expanding the company’s role as a regional energy supplier.

“We started building the Green Grid for our own operations, but we could see strong demand for cheap, green, reliable power across the Pilbara and an opportunity to supply other customers too,” Otranto said.

“This agreement is an important first step and cements our role as an energy supplier. It will help power PLS’ expansion, support economic growth in the region, and create a new, long-term revenue stream for Fortescue.”

PLS expects the new power arrangement to reduce Pilgangoora’s power-related emissions intensity by up to 80 per cent from its 2022–23 baseline by 2030.

The agreement remains subject to conditions, including construction arrangements and regulatory approvals, while PLS will retain and expand on-site generation to manage potential supply interruptions.

“PLS is our first customer, with a strong pipeline of others across the Pilbara looking to our Green Grid for greater choice and flexibility in how they source their power,” Otranto said.

Subscribe to Australian Mining and receive the latest news on product announcements, industry developments, commodities and more.

Australian Mining.

Source: Australian Mining · 行业资讯 · australianmining.com.au

Licence: 负责人声明许可;来源异议或指示可逐项收紧

The original source is traceable; the Chinese content is written or translated with AI assistance ; check the original for details.

Related coverage

Representative reportFrom the party involved or an official body

福蒂斯丘(Fortescue)与PLS签署20年绿电供电协议,首次向外部客户供电

Fortescue · 官方动态 · 2026-10-27

福蒂斯丘(Fortescue)签署首份电力购买协议,将在20年内每年向PLS Group的Pilgangoora Operation供应至少325GWh电力,供电预计2029年开始。福蒂斯丘将建设约25公里、220kV输电线路连接该矿区与其Green Grid,PLS承担线路全部费用并拥有其中20公里,以支持该锂矿商近期获批的19亿澳元扩建项目。福蒂斯丘称其规划660公里输电网络中已有550公里建成,Green Grid已有超过1.3GW风光装机投运或在建。

LatestFrom the party involved or an official body

福蒂斯丘(Fortescue)与PLS签署20年绿电供电协议,首次向外部客户供电

Fortescue · 官方动态 · 2026-10-27

福蒂斯丘(Fortescue)签署首份电力购买协议,将在20年内每年向PLS Group的Pilgangoora Operation供应至少325GWh电力,供电预计2029年开始。福蒂斯丘将建设约25公里、220kV输电线路连接该矿区与其Green Grid,PLS承担线路全部费用并拥有其中20公里,以支持该锂矿商近期获批的19亿澳元扩建项目。福蒂斯丘称其规划660公里输电网络中已有550公里建成,Green Grid已有超过1.3GW风光装机投运或在建。