Vizsla Silver将Panuco银金矿首次产银目标推迟至2028年下半年

VIZSLA SILVER PROVIDES UPDATE ON PANUCO PROJECT DEVELOPMENT

Public on this site

AI summary

Vizsla Silver(Vizsla Silver)将墨西哥锡那罗亚州全资Panuco银金矿的首次产银目标从2027年下半年推迟至2028年下半年,原因是许可、现场准备和建设时间安排。公司称M3 Engineering & Technology已完成约50%的工程设计,项目约85%的选厂设备已订购,EPCM、矿山设计与设备供应三份关键合同已授出,主采矿合同尚待授出。公司同时表示正与墨西哥联邦当局合作加强安保,为分阶段返场做准备,并承诺向Vizsla Foundation初始出资500万美元。