Eldorado Gold 在 Skouries 启动首批两台美卓尾矿压滤机

Eldorado Gold starts up first two Metso tailings filter presses at Skouries

Public on this site

AI summary

Eldorado Gold 位于希腊北部的 Skouries 矿山首批两台尾矿压滤机已投入运行,工厂正连续运转并逐步提高处理量。该尾矿过滤设施共配置六台美卓压滤机,其中五台运行、一台备用;处理硫化物矿石时需四台运行压滤机支撑商业化生产,达到设计产能则需五台。其余四台压滤机的调试预计于 2026 年 11 月完成。Skouries 在矿山全生命周期内预计年均产金 140,000 盎司、产铜 67 MIb。

Text · original

The Chinese translation is being made; the original is shown for now.

Eldorado Gold says the first two tailings filter presses at its Skouries mine in northern Greece are now operational, marking another important milestone toward commercial production.

With these filter presses online, the plant is operating continuously and progressively increasing throughput as commissioning advances and the remaining filter presses are brought online.

The Skouries tailings filtration facility comprises six Metso filter presses which includes five operating units and one installed spare. Four operating filter presses are required to support commercial production on sulphide ore and five to achieve nameplate throughput. The sixth unit will provide installed spare capacity, providing operational flexibility and enabling maintenance activities with no loss of throughput. Commissioning of the remaining four filter presses is expected to be completed in November 2026.

“Bringing the filter presses online is an important commissioning milestone,” Christian Milau, President and Chief Executive Officer, says. “Filtered tailings are a cornerstone of Skouries’ design and a key component of our Integrated Extractive Waste Management strategy. They reflect our commitment to implementing modern mining technologies that enhance environmental performance, support long-term operational reliability and maximize water recovery.”

Commissioning and ramp-up activities continue across Skouries, with the focus on progressively increasing throughput and optimising plant performance as the operation advances toward commercial production. Skouries is expected to produce on average 140,000 oz of gold and 67 MIb of copper annually over the life of mine.

The post Eldorado Gold starts up first two Metso tailings filter presses at Skouries appeared first on International Mining.

Source: International Mining · 矿业新闻 · im-mining.com

Licence: 负责人声明许可;来源异议或指示可逐项收紧

The original source is traceable; the Chinese content is written or translated with AI assistance ; check the original for details.

Something wrong? Tell us

Event follow-ups

See the full event

More actions