Skip to content
Australian Mining · 行业资讯· Ethan Benedicto·· 1 h agoAI score48.0

Maritana Minerals 启动 Black Swan 加工枢纽混凝土施工

Maritana kicks off major Black Swan construction works

Public on this site

AI summary

Maritana Minerals 已在西澳 Black Swan 加工枢纽启动混凝土施工,项目由此从准备阶段转入建设阶段,目标是在 2027 年下半年实现首次产金。施工方 Civitech 于 10 月启动新碳浸(CIL)回路的基础工程,该加工厂年处理能力为 250 万吨。公司同时把与 GR Engineering Services 的早期工程协议延长至 2026 年 12 月 31 日,追加投入 1990 万美元,以维持详细设计、采购和长周期设备订单。

Text · original

The Chinese translation is being made; the original is shown for now.

查看配图:Medallion
Image: STOCKSTUDIO/stock.adobe.com

Maritana Minerals has commenced concrete construction at its Black Swan processing hub (BSPH) in Western Australia, marking a significant step towards first gold production in the second half of 2027.

The development follows completion of the principal demolition program, with work now underway on the foundations of the new carbon-in-leach (CIL) circuit at the 2.5-million-tonne-per-annum processing facility.

Construction contractor Civitech commenced the CIL tank ring-beam foundations during October, completing reinforcement and formwork before progressing to concrete placement.

Further foundation works and tank erection preparations are underway as additional construction areas become available.

Maritana managing director and chief executive officer Grant Haywood said the latest activities demonstrated the project’s transition towards construction.

“The commencement of concrete works for the new CIL circuit is another visible step forward at the BSPH,” Haywood said.

“With the principal demolition program complete, SAG mill liner removal underway and the ROM pad expansion progressing, the site is moving steadily from preparation into construction.”

Meanwhile, Maritana has extended its early works agreement with GR Engineering Services (GRES) to December 31, 2026, committing an additional $19.9 million while the engineering, procurement and construction (EPC) contract is finalised.

The extension will maintain detailed engineering, procurement and site activities, including long-lead equipment orders for the regeneration kiln, electrowinning cells and other processing infrastructure.

Work on Black Swan’s existing grinding circuit also continues, with semi-autogenous grinding (SAG) mill liner removal underway and Hofmann Engineering selected for specialist refurbishment activities.

The existing mill was previously rotated for the first time in approximately 17 years, allowing detailed inspections and refurbishment planning to progress, with Maritana securing the final statutory approvals required for processing plant construction in September.

The latest update also outlined a staged tailings strategy, with a planned lift of the existing TSF4 facility expected to provide approximately three years of processing capacity.

This would allow Maritana to develop a new tailings facility, TSF5, alongside initial operations.

“Our staged tailings strategy, built on a lift of the existing TSF4, is planned to provide around three years of processing capacity and de-risks the path to first gold, while the appointment of Chris Mardon as general manager operations strengthens our readiness to move from construction into operations,” Haywood said.

The company has appointed Mardon to oversee operational readiness and commissioning preparations.

Meanwhile, expansion of the run-of-mine pad is progressing to accommodate ore from multiple deposits across Maritana’s Goldfields portfolio.

The work follows recent high-grade drilling success at Boorara, where Maritana intersected 36m at 3.53 grams per tonne of gold beneath the planned southern open pit.

Mining at Boorara is targeted to restart in mid-2027, providing feed for Black Swan’s planned commissioning and production ramp-up.

“This is more than a plant refurbishment: we are building a regional gold processing hub for multiple Kalgoorlie ore sources, targeting first gold in H2 CY2027,” Haywood said.

Subscribe to Australian Mining and receive the latest news on product announcements, industry developments, commodities and more.

Australian Mining.

Source: Australian Mining · 行业资讯 · australianmining.com.au

Licence: 负责人声明许可;来源异议或指示可逐项收紧

The original source is traceable; the Chinese content is written or translated with AI assistance ; check the original for details.

Something wrong? Tell us

Event follow-ups

See the full event

More actions