Skip to content
International Mining · 矿业新闻·· 2026-10-09AI score40.0

FLSmidth获智利铜矿磨矿设备订单,含HPGR与球磨机

FLS wins another copper mine order in Chile for grinding tech including HPGR & ball mill

Public on this site Time not recorded

AI summary

FLSmidth(FLS)获得智利一座铜矿的磨矿技术订单,将为其新建磨矿生产线供应1台24/17高压辊磨机(HPGR)和1台27′ x 46′、19.6 MW无齿轮球磨机,并提供衬板、安装调试及备件与现场服务,安装调试计划于2027年进行。订单金额约1.75亿丹麦克朗,已于2026年第三季度入账,不影响FLS对2026年全年的财务指引。

Text · original

The Chinese translation is being made; the original is shown for now.

FLSmidth (FLS) has received another major order in Chile, this time to supply core grinding technologies for the establishment of a new grinding line at a copper mine.

The order marks the next phase of FLS’s long-standing partnership with the customer, following close collaboration on the engineering solutions for the expansion project. The scope of supply comprises one 24/17 High-Pressure Grinding Roll (HPGR) and one 27′ x 46′, 19.6 MW gearless ball mill, together with FLS ARMOUR查看配图:™ mill liners, installation, commissioning, start-up support and an agreement covering spare parts supply and extended on-site services. Installation and commissioning are scheduled for 2027.

FLS stated: “As the market leader in HPGR technologies, FLS brings decades of operating experience and a proven track record of delivering energy-efficient, high-throughput grinding solutions that help customers reduce operating costs and improve sustainability.”

“We are proud to build on our long-standing relationship with the customer and to have been selected as a technology and service partner for this important expansion project. The order reflects the trust established through our collaboration and combines FLS’s energy-efficient HPGR and ball mill solutions with installation, commissioning and ongoing service support. Together, these solutions will help enable the planned increase in processing capacity and contribute to higher production and lower unit costs,” commented Qasim Abrahams, Products Business Line President at FLS.

The value of the order totals approximately DKK 175 million and was booked in the third quarter of 2026. The order does not change FLS’s financial guidance for the full year 2026.

FLS says its HPGRs deliver highly energy-efficient ore comminution, helping customers increase throughput, lower operating costs and improve downstream mineral recovery. “By creating microcracks that weaken the ore and improve mineral liberation, our HPGR technology reduces the power required for subsequent grinding, while robust wear components and advanced process control support greater uptime and consistent performance.”

The post FLS wins another copper mine order in Chile for grinding tech including HPGR & ball mill appeared first on International Mining.

Source: International Mining · 矿业新闻 · im-mining.com

Licence: 负责人声明许可;来源异议或指示可逐项收紧

The original source is traceable; the Chinese content is written or translated with AI assistance ; check the original for details.

Something wrong? Tell us

Event follow-ups

See the full event

More actions