Aria Resources 公布津巴布韦 Dokwe 金矿项目可行性研究进展

Aria Resources announces Dokwe project feasibility programme update

Public on this site

AI summary

Aria Resources 就津巴布韦 1.6 Moz Dokwe 金矿项目公布可行性研究进展:Dokwe 北部 2,200m 水井钻探正在施工以确定选矿用水水源,Xinhai 与 IMO 的冶金试验同步进行,Dokwe Central 岩土钻探已完成。公司预计今年年底前发布修订后的矿石储量声明,并将在完成约 11,000m 勘探与资源钻探后推进独立矿产资源量估算。

Text · original

The Chinese translation is being made; the original is shown for now.

查看配图:Image: AI-generated image. Not a photograph. Copyright © Conventus – AI-generated content. None of the material may be reproduced or used in other contexts without written permission.

Image: AI-generated image. Not a photograph. Copyright © Conventus – AI-generated content. None of the material may be reproduced or used in other contexts without written permission.

Published by

Ariana Resources plc, amineral exploration and development company advancing the 100% owned, 1.6 Moz Dokwe Gold Project in Zimbabwe, announcse an update on its Feasibility Study Programme for the Project.

Highlights include:

  • 2,200m of water bore drilling underway in an area hosting a potential aquifer to the north of Dokwe, in order to define a source for processing water.
  • Metallurgical testwork underway with Xinhai and IMO, in China and Australia respectively.
  • Geotechnical drilling completed at Dokwe Central, which provides new data for the planning of the expected Dokwe Central open-pit.
  • 2,300m of RC drilling due to commence for infrastructure area sterilisation and associated exploration.
  • Aeromagnetic and LiDAR survey to commence, which will enable better exploration planning and targeting ahead of future drilling programmes.

Dr. Kerim Sener, Managing Director, commented:

“We are making excellent headway with the Feasibility Study programme for the Dokwe Gold Project in Zimbabwe on several very active fronts. With the recent completion of exploration and resource drilling programmes totalling c.11,000m, we are now advancing our work towards an Independent Mineral Resource Estimate. This will become the final MRE for the purposes of the Feasibility Study. 

“Furthermore, we are advancing towards a revised Ore Reserve statement which we expect towards the end of this year. 

“Various other project developments are underway, notably the commencement of our c.2,200m water drilling programme to ensure we will have sufficient water supply for the processing plant. 

“Beyond this, we are preparing to commence several new exploration and development activities across the project. Ultimately, we want to test systematically the remaining 10km of identified prospective shear zones that are untested by drilling, which to date has only examined 3km of strike.

“We also note the significant local support for the development of the project and look forward to continuing our work with the local community to make a meaningful and positive social impact over the years ahead.”

Source: MININGMETALnews · 行业资讯 · miningmetalnews.com