Medallion Metals 旗下 Cosmic Boy 项目临近加工,目标 11 月启动黄金销售

Medallion targets November gold sales as Cosmic Boy nears processing

Public on this site

AI summary

Medallion Metals 的 Cosmic Boy 项目临近加工阶段,公司目标在 11 月实现黄金销售。周一金价一度突破 US$4170/盎司,受避险需求和美国利率不确定性提振。

Text · original

The Chinese translation is being made; the original is shown for now.

Medallion Metals is nearing production as gold briefly traded above US$4170/ounce on Monday, buoyed by safe-haven demand and uncertainty over US interest rates.

The MOU supports Metallium’s plan to develop a national network of e-waste processing facilities, strategically located near major e-waste collection hubs, rapidly expanding U.S. data centre industrial parks and regional industrial corridors with strong logistics and waste generation.

Source: The Australian Mining Review · 行业资讯 · australianminingreview.com.au

Licence: 负责人声明许可;来源异议或指示可逐项收紧

The original source is traceable; the Chinese content is written or translated with AI assistance ; check the original for details.

Related coverage

Representative report

Medallion Metals 为 Cosmic Boy 选厂锁定至少 20 万吨第三方矿石

Australian Mining · 行业资讯 · 2026-11-02 09:53

Medallion Metals 已为其西澳 Cosmic Boy 选厂锁定至少 20 万吨第三方含金矿石,用于在 Kundip 硫化物矿石于 2027 年交付前启动加工。该安排来自公司 9 月季度活动报告,第三方金矿已开始交付,新碳柱罐在季度后安装,破碎回路于 10 月启动调试,公司目标 10 月开始首次加工、11 月实现首次生产和销售。Cosmic Boy 改造工程由 GR Engineering Services 承接,9 月中旬完成约 30%,改造后设计年处理 65 万吨 Ravensthorpe 硫化物矿石,针对 Kundip 矿石的调试目标为 2027 年第二季度。

Latest

Medallion Metals 为 Cosmic Boy 选厂锁定至少 20 万吨第三方矿石

Australian Mining · 行业资讯 · 2026-11-02 09:53

Medallion Metals 已为其西澳 Cosmic Boy 选厂锁定至少 20 万吨第三方含金矿石,用于在 Kundip 硫化物矿石于 2027 年交付前启动加工。该安排来自公司 9 月季度活动报告,第三方金矿已开始交付,新碳柱罐在季度后安装,破碎回路于 10 月启动调试,公司目标 10 月开始首次加工、11 月实现首次生产和销售。Cosmic Boy 改造工程由 GR Engineering Services 承接,9 月中旬完成约 30%,改造后设计年处理 65 万吨 Ravensthorpe 硫化物矿石,针对 Kundip 矿石的调试目标为 2027 年第二季度。