The Northern Miner · 行业资讯· Henry Lazenby·· 19 d agoAI score62.0

Magna Mining 批准 Crean Hill 镍铜矿建设,目标 2027 年底开始售矿

Magna targets late-2027 ore sales at Crean Hill

Public on this site

AI summary

Magna Mining 董事会批准安大略省 Crean Hill 镍铜矿于明年上半年开工建设,目标 2027 年底开始销售矿石、2030 年初进入商业生产。新发布的预可行性研究估算初始资本支出 1.27 亿美元,商业生产期 12 年,税后净现值 2.51 亿美元、内部收益率 43%。商业生产期年均应付产量约 950 万磅铜、750 万磅镍及近 4.2 万盎司铂钯金合计,贵金属约占收入的 39%。

Text · original

The Chinese translation is being made; the original is shown for now.

查看配图The road to the past-producing Crean Hill nickel-copper mine. Credit: Magna Mining

Posted By: Henry Lazenby October 21, 2026

Magna Mining (TSX: NICU; US-OTC: MGMNF) on Tuesday approved construction to start next year at its past-producing Crean Hill project in Ontario, advancing plans to become a three-mine producer in the Sudbury Basin.

A new prefeasibility study, also released Tuesday, estimates initial capital spending of $127 million (US$90.4 million) for 12 years of commercial production. Formal construction at the project, about 350 km northwest of Toronto, is expected to begin in the first half of next year.

“Crean Hill also benefits from a balanced mix of copper, nickel and precious metals production, providing meaningful exposure to seven payable metals without an overreliance on any single commodity,” CEO Jason Jessup said in a release.

The decision adds another development to Magna’s operating McCreedy West mine and Levack restart earlier this month. Desjardins analyst Bryce Adams Wednesday called the update “slightly positive,” saying board approval reduced risk on the path to production. The study’s valuation broadly matched his model, although initial capital was about a third above his $95-million forecast.

Shares gained almost 1% to $2.18 apiece by mid-Wednesday in Toronto, valuing Magna at about $680 million. Adams rates the stock “buy,” with a speculative risk designation and a $5 price target.

$251M value

The base case values Crean Hill at $251 million after tax, using a 7% discount rate, with an internal rate of return of 43%. The estimated 1.5-year payback starts after the three-year construction and ramp-up period.

Those estimates assume copper at US$5.10 per lb., nickel at US$8 per lb. and gold at US$3,600 per oz., alongside platinum at US$1,500 and palladium at US$1,200 per ounce.

During commercial production, annual payable output would average 9.5 million lb. copper, 7.5 million lb. nickel and nearly 42,000 oz. of platinum, palladium and gold combined, according to the study. Precious metals would provide about 39% of revenue.

2030 commercial output

Crean Hill last operated in 2002. Magna acquired the property in 2022 and the revamped project’s first ore sales are expected in late 2027, ahead of commercial production in early 2030. Magna plans to spread initial capital spending over three years, with $33 million next year, $35 million in 2028 and $59 million in 2029.

The company calculates a net initial funding requirement of $72.4 million after $17.2 million in anticipated refundable tax credits and $37.4 million in projected operating cash flow during the ramp-up.

While the construction bill remains the same, Magna’s lower funding estimate assumes it receives expected tax credits and earns as much as forecast from early ore sales.

The company holds cash and equivalents at about $175 million, calculated from Magna’s June balance plus net proceeds from Alpayana’s $140-million equity investment, which closed Aug. 28. The funds support development across Magna’s portfolio.

Magna plans to sell Crean Hill ore to an existing third-party mill in Sudbury. Miners would initially use a new ramp descending from surface, then restore the former No. 2 shaft to hoist ore as workings deepen.

Print

By continuing to browse you agree to our use of cookies. To learn more, click more information

Source: The Northern Miner · 行业资讯 · northernminer.com

Licence: 负责人声明许可;来源异议或指示可逐项收紧

The original source is traceable; the Chinese content is written or translated with AI assistance ; check the original for details.

Related coverage

Representative reportFrom the party involved or an official body

Magna Mining 公布 Crean Hill 预可行性研究结果,2027 年启动建设

Magna Mining · 官方动态 · 2026-10-21 18:45

Magna Mining 公布 Crean Hill 项目 NI 43-101 预可行性研究结果,规划 12 年商业矿山寿命、11.4 百万短吨可信储量,年均可支付铜当量产量 35.5 百万磅,全维持成本 US$3.55/磅。基准情形下税后净现值(7%)为 2.51 亿加元、税后内部收益率 43.4%、投资回收期 1.5 年,初始资本 1.27 亿加元,扣除可退还税收抵免和商业化生产前运营现金流后净初始资金需求 7240 万加元。董事会已批准建设,正式开工预计在 2027 年上半年,首批矿石销售在 2027 年底,商业生产在 2030 年初;公司同时已在 Crean Hill 启动勘探钻探。

LatestFrom the party involved or an official body

Magna Mining 公布 Crean Hill 预可行性研究结果,2027 年启动建设

Magna Mining · 官方动态 · 2026-10-21 18:45

Magna Mining 公布 Crean Hill 项目 NI 43-101 预可行性研究结果,规划 12 年商业矿山寿命、11.4 百万短吨可信储量,年均可支付铜当量产量 35.5 百万磅,全维持成本 US$3.55/磅。基准情形下税后净现值(7%)为 2.51 亿加元、税后内部收益率 43.4%、投资回收期 1.5 年,初始资本 1.27 亿加元,扣除可退还税收抵免和商业化生产前运营现金流后净初始资金需求 7240 万加元。董事会已批准建设,正式开工预计在 2027 年上半年,首批矿石销售在 2027 年底,商业生产在 2030 年初;公司同时已在 Crean Hill 启动勘探钻探。