Fondos mineros reactivan el hospital de Antofagasta de la Sierra y la obra apunta a terminarse en 2027
Public on this site
阿根廷卡塔马卡省安托法加斯塔(Antofagasta) de la Sierra的新医院在停工后于8月复工,资金来自Salar del Hombre Muerto矿业信托,截至10月底本阶段工程进度超过29%,高于计划的26.91%。项目建筑面积1.355平方米,由ITALCA Constructora SRL承建,工期十个月,预计2027年下半年完工。医院规划设住院、影像诊断、检验、急诊和远程医疗,位于该国锂项目集中的普纳地区。