Brightstar Resources 旗下 Goldfields 项目选矿厂建设进度过半,预计 2027 年 6 月首次产金

Brightstar reaches halfway mark on road to first gold

本站公开

AI 导读

Brightstar Resources 位于西澳大利亚的 Goldfields 项目新建 Laverton 选矿厂建设进度已达 50%,工程、采购与施工(EPC)挣值完成过半,10 月工程设计进度突破 90%,仍按计划在 2027 年 6 月首次产金。该厂年处理能力为 150 万吨,建设仍在批准的预算内,SAG 磨机部件已到场,磨矿与分级区域钢结构安装已启动。公司还完成了 Laverton 的 Boomers Mining 住宿营地收购,Lord Byron 露天矿品位控制钻探已于 10 月启动,首次爆破目标定在第四季度。

正文 · 原文

中文译文生成中,先为你显示原文。

查看配图:Brightstar Gold
Image: sashagrunge/stock.adobe.com

Brightstar Resources has reached a key construction milestone at its Goldfields Project in Western Australia, with its new Laverton processing plant remaining on schedule for first gold in June 2027.

The company reported that engineering, procurement and construction (EPC) earned value had reached 50 per cent completion, while engineering work passed the 90 per cent milestone during October.

According to Brightstar, construction of the 1.5-million-tonne-per-annum processing plant remains within its approved budget, with major equipment deliveries and infrastructure works progressing.

Brightstar managing director Alex Rovira said the latest milestones were bringing the project closer to production.

“October marked another month of disciplined execution at the Goldfields Project. With EPC earned value now at the halfway mark and the 90 per cent engineering milestone behind us, the project continues to move decisively towards first gold in June 2027,” he said.

October activities included the arrival of key semi-autogenous grinding (SAG) mill components, completion of primary crusher concrete works and the commencement of structural steel installation in the grinding and classification area.

Two carbon-in-leach tanks have also been fabricated to full height, while borefield testing and water transfer to the plant site have commenced.

The company has also completed the acquisition of the 223-room Boomers Mining accommodation camp in Laverton to support construction activities and provide accommodation for its future operational workforce.

Brightstar said the facility would accommodate workers during peak construction periods and future plant shutdowns, while providing a permanent base for mining, processing and other site-based teams.

Meanwhile, preparations are progressing at the Lord Byron open pit, where grade control drilling commenced in October.

Drill-and-blast contractor Aquirian has mobilised to site, with Brightstar targeting its first blast in the December quarter, ahead of schedule. Open-pit mining is expected to commence early in the March quarter of 2027.

The company’s January feasibility study outlined a production target exceeding 75,000 ounces of gold annually over six years, providing a longer-term outlook for the Goldfields Project as construction advances.

Rovira said the acquisition of the Boomers camp would support the company’s transition into production.

“Our acquisition of the Boomers Mining Accommodation Camp is a deliberate investment in Laverton and in the long-term future of our operations,” he said.

Subscribe to Australian Mining and receive the latest news on product announcements, industry developments, commodities and more.

Australian Mining.

来源:Australian Mining · 行业资讯 · australianmining.com.au

许可:负责人声明许可;来源异议或指示可逐项收紧

原始来源可追溯;中文内容由 AI 辅助生成或翻译,核对细节请看原文。

内容有误?告诉我们

事件后续

查看完整事件

更多操作