AI 导读

IGO Limited宣布西澳Nova镍矿开采与选冶已结束,镍产量21,340吨,比寿命期指引上限高7%,铜和钴也超出指引上限。该矿由Barminco于2015年建成地下矿,11年间完成超52公里掘进、开采超1450万吨矿石。IGO预计未来数周完成将Nova出售给Global Lithium Resources的交易,后者计划把选厂和基础设施改用于其Manna锂项目。

正文 · 原文

中文译文生成中,先为你显示原文。

IGO Limited says mining and processing at the Nova Nickel Operation, in Western Australia, have concluded, almost a decade after production began.

Following the final reconciliation of production, Nova finished above the top end of its life of mine guidance for nickel, copper and cobalt, the company says. Nickel production of 21,340 t finished 7% above the top end of guidance.

Nova ended up being one of the few Australian operations to test out battery-electric equipment, with, among other equipment, a Normet Charmec MC 605 VE SmartDrive battery-powered emulsion charger and a Sandvik DL422iE production drill in use there through contractor Barminco.

IGO Managing Director and Chief Executive Officer, Ivan Vella, said: “Nova has been a high-quality, low-cost operation for almost a decade, and it has finished as strongly as it started. Delivering this in the final stages of a mine’s life, when operations are often at their hardest, reflects the capability and commitment of the Nova team. I thank them and our contractors for their professionalism right through to the final tonne.”

Barminco, which trucked the last ore to surface from underground, established the underground mine at Nova in 2015. Over the past 11 years, it completed over 52 km of development, mined over 14.5 Mt of ore, completed over 1.6 million metres of production drilling, and trucked over 59 million TKMs.

The Nova team is now completing demobilisation at site.

IGO expects to complete the divestment of Nova to Global Lithium Resources Limited in the coming weeks. As previously announced, Global Lithium intends to repurpose Nova’s processing plant and infrastructure for its Manna lithium project.

The post IGO concludes mining at Nova nickel operation in Western Australia appeared first on International Mining.

来源:International Mining · 矿业新闻 · im-mining.com

许可:负责人声明许可;来源异议或指示可逐项收紧

原始来源可追溯;中文内容由 AI 辅助生成或翻译,核对细节请看原文。

相关报道

代表稿当事方或官方发布

IGO 旗下 Nova 镍矿结束开采,产量与成本均超指引

IGO Limited · 官方动态 · 2026-11-09

IGO Limited(IGO)宣布,Nova 镍矿在投产近十年后结束采矿与选矿。最终核算显示,全生命周期镍产量 21,340t,比指引上限高 7%;铜产量 9,517t、钴产量 765t,均高于指引区间;可支付镍现金成本 A$3.90/lb,比更新后指引下限低 8%。现场人员正在撤场,IGO 预计未来数周完成将 Nova 出售给 Global Lithium Resources Limited,后者计划把选矿厂和基础设施改用于 Manna 锂项目。

最新进展当事方或官方发布

IGO 旗下 Nova 镍矿结束开采,产量与成本均超指引

IGO Limited · 官方动态 · 2026-11-09

IGO Limited(IGO)宣布,Nova 镍矿在投产近十年后结束采矿与选矿。最终核算显示,全生命周期镍产量 21,340t,比指引上限高 7%;铜产量 9,517t、钴产量 765t,均高于指引区间;可支付镍现金成本 A$3.90/lb,比更新后指引下限低 8%。现场人员正在撤场,IGO 预计未来数周完成将 Nova 出售给 Global Lithium Resources Limited,后者计划把选矿厂和基础设施改用于 Manna 锂项目。