Gunnison hits rich copper and zinc in Arizona

本站公开

AI 导读

Gunnison Copper 在亚利桑那州 Strong & Harris 矿床确认高品位铜锌矿带,钻孔 SHM-2 自 160 米深处见矿 94.8 米,品位 1.39% 铜、2.29% 锌。其中自 175.6 米起 12.2 米区间品位达 5.15% 铜、11.99% 锌及 16.38 克/吨银。公司称下一步将开展浮选试验,评估硫化物矿石能否产出可销售的铜、锌精矿,银作为可计价副产品。

正文 · 原文

中文译文生成中,先为你显示原文。

查看配图Copper cathodes at Gunnison's Johnson Camp mine processing facility in Arizona. Credit: Gunnison Copper via Facebook.

By: Northern Miner Staff November 10, 2026

Gunnison Copper (TSX: GCU; NYSE-A: GUNN) has confirmed a high-grade copper-zinc zone at its Strong & Harris deposit in Arizona as it tests whether a concentrator could add another processing option to its development plans.

Drill hole SHM-2 cut 94.8 metres grading 1.39% copper and 2.29% zinc from 160 metres depth, the company said Tuesday. That included 12.2 metres of 5.15% copper, 11.99% zinc and 16.38 grams silver per tonne from 175.6 metres

“Our next priority is to understand how best to recover that metal,” CEO Craig Hallworth said Tuesday.

The drilling confirms mineralization already represented in the resource model. Flotation tests will assess whether sulphide material can yield saleable copper and zinc concentrates, with silver as a payable byproduct. Recoveries and economics must be established before a concentrator could enter a development plan.

Processing options

The Gunnison project lies about 100 km east of Tucson. Its March preliminary economic assessment envisaged open-pit mining and heap leaching, followed by solvent extraction and electrowinning to produce finished copper cathode. The study includes inferred resources, and its economic conclusions remain preliminary.

Strong & Harris held 69 million inferred tonnes at 0.49% copper, 0.56% zinc and about 4.1 grams silver as of Jan. 23, containing about 335,700 tonnes copper, 388,100 tonnes zinc and 9 million oz. silver, according to the March technical study.

Gunnison estimates the true thickness of the 94.8-metre intersection at 82.1 metres and the richer 12.2-metre interval at 10.5 metres.

The company already produces copper at nearby Johnson Camp, where it is demonstrating Rio Tinto’s (NYSE, LSE, ASX: RIO) Nuton leaching technology. Nuton agreed in September to pay Gunnison $8 million (C$11.3 million) after the partners expanded the plan to mine additional material during the 2027–2029 demonstration period.

Gunnison shares fell 1.3% to 38.5¢ apiece Tuesday morning in Toronto, valuing the company at about C$198 million ($141 million). The stock has traded between 27.5¢ and 70¢ apiece over the past year.

Print

来源:The Northern Miner · 行业资讯 · northernminer.com

许可:负责人声明许可;来源异议或指示可逐项收紧

原始来源可追溯;中文内容由 AI 辅助生成或翻译,核对细节请看原文。

相关报道

代表稿当事方或官方发布

Gunnison Copper 确认 Strong & Harris 高品位铜锌银硫化物矿段,见矿40英尺铜品位5.15%、锌11.99%

Gunnison Copper · 官方新闻 · 2026-11-10 19:00

Gunnison Copper Corp. 公布亚利桑那州 Gunnison 铜项目及 Strong & Harris 卫星矿床 2026-2027 钻探计划的初步化验结果,钻孔 SHM-2 在 311 英尺、铜品位 1.39%、锌品位 2.29% 的矿化段内见 40 英尺铜品位 5.15%、锌品位 11.99%、银品位 16.38 g/t 的高品位块状硫化物。Gunnison 项目钻孔 NSM-18 见 790.3 英尺铜品位 0.46%,NSM-22 见 738.3 英尺铜品位 0.43%。公司同时在 FLSmidth 开展浮选试验,评估硫化物精矿路线及锌、银副产品回收,计划总进尺约 138,000 英尺的钻探已完成 27,953 英尺。

最新进展当事方或官方发布

Gunnison Copper 确认 Strong & Harris 高品位铜锌银硫化物矿段,见矿40英尺铜品位5.15%、锌11.99%

Gunnison Copper · 官方新闻 · 2026-11-10 19:00

Gunnison Copper Corp. 公布亚利桑那州 Gunnison 铜项目及 Strong & Harris 卫星矿床 2026-2027 钻探计划的初步化验结果,钻孔 SHM-2 在 311 英尺、铜品位 1.39%、锌品位 2.29% 的矿化段内见 40 英尺铜品位 5.15%、锌品位 11.99%、银品位 16.38 g/t 的高品位块状硫化物。Gunnison 项目钻孔 NSM-18 见 790.3 英尺铜品位 0.46%,NSM-22 见 738.3 英尺铜品位 0.43%。公司同时在 FLSmidth 开展浮选试验,评估硫化物精矿路线及锌、银副产品回收,计划总进尺约 138,000 英尺的钻探已完成 27,953 英尺。

内容有误?告诉我们

事件后续

查看完整事件

更多操作