MINING.COM· FREDERIC TOMESCO·· 7 天前AI 评分63.0

Endeavour 因坡道下沉暂停布基纳法索 Mana 金矿地下采矿

Endeavour halts Burkina gold underground as ramp sinks

本站公开

AI 导读

Endeavour Mining 在布基纳法索 Mana 金矿一处通道下沉后暂停地下采矿,10 月 28 日的事故限制了经采空的 Wona 露天坑进入 Dangouna 和 Aviera 两个地下入口,人员已撤离、无人受伤,三个在产地下入口全部停止作业,等待地压稳定性评估与修复。公司称即使第四季度 Mana 不再采矿,仍有望实现全年产量与全维持成本目标,此前给出的 2026 年产量指引为 109 万至 127 万盎司,并计划在 11 月 12 日发布三季度业绩时说明地压评估与修复方案。Mana 今年上半年产量由上年同期的 8.7 万盎司降至 6.8 万盎司,7 月公司已预警全年产量将低于 15.5 万至 18 万盎司的原目标下限。

正文 · 原文

中文译文生成中,先为你显示原文。

Endeavour Mining (TSX, LSE: EDV) suspended underground mining at its Mana gold mine in Burkina Faso after part of an access road sank, adding another setback at an operation already expected to miss its annual production target.

The Oct. 28 incident restricted access to two underground entrances, Dangouna and Aviera, through the depleted Wona open pit, Endeavour said Monday. Workers were evacuated, nobody was injured and local authorities were notified. Mining has been stopped at all three active underground entrances while specialists assess ground stability and repairs.

Endeavour didn’t immediately disclose the cause of the incident or announce a restart date.

Despite the incident, Endeavour said it remains on track to hit full-year production and all-in sustaining cost targets even if no further mining occurs at Mana in the fourth quarter. Endeavour previously said it expected 2026 output to range between 1.09 million oz. and 1.27 million ounces.

“The overall impact will depend on how long portal remediation takes (we think one to two quarters) and on whether open pit feed, subject to permitting, can supplement throughput,” National Bank Financial mining analyst Mohamed Sidibé said Monday in a note.

Repair plan

Endeavour is considering restarting and accelerating mining through the Wona entrance, which remains accessible, and drawing on nearby open pits to limit lost production. It plans to outline the ground assessment and repair plan when it reports third-quarter results on Nov. 12.

The disruption follows an earlier ground-stability concern. In July, Endeavour disclosed that mining at Aviera had paused that month to monitor a surface fracture in the depleted Wona pit above the deposit. At the time, it said the fracture didn’t affect active ore zones and anticipated resuming work around mid-third quarter, subject to monitoring.

Monday’s announcement didn’t say whether that fracture and the latest subsidence were connected.

The event disclosed Monday “appears to have occurred on a structure parallel to the July one, though it is too early to tell if they are related,” Sidibé said. Mana represents about 5% of the company’s net asset value, according to his calculations.

Along with the Houndé mine, Mana is one of Endeavour’s two producing assets in Burkina Faso. In West Africa, the company also produces gold in Côte d’Ivoire and Senegal.

Earlier depletion

Mana’s difficulties also extend beyond ground conditions. Endeavour warned in July that annual output would fall below the bottom of its original 155,000–180,000 oz. target, with sustaining costs exceeding guidance. It attributed the weakness partly to earlier depletion of the higher-grade Siou underground deposit after unsuccessful drilling to extend its resources, and delayed mining at the Bana Camp open pit.

First-half production fell to 68,000 oz. from 87,000 oz. a year earlier, a decline of about 22%. Mana accounted for about 12% of Endeavour’s first-half output.

London-based Endeavour owns 85% of Mana, with Burkina Faso’s government holding the balance. The mine lies about 60 km north of Houndé.

Mana’s processing plant began operating in 2008, and the mine shifted to fully underground production in 2024. It produced 173,000 oz. last year.

Endeavour’s longer-term strategy is to extend its operating life beyond a decade by expanding underground deposits and evaluating nearby surface targets. Restoring reliable access to those underground workings is now the immediate priority for the operation.Top of FormBottom of Form

Toronto-traded shares of Endeavour rose 0.9% to C$70.33 Monday morning, valuing the company at about C$17 billion ($12.2 billion). The stock has traded between C$53.37 and C$98.71 in the past year.

来源:MINING.COM · mining.com

许可:负责人声明许可;来源异议或指示可逐项收紧

原始来源可追溯;中文内容由 AI 辅助生成或翻译,核对细节请看原文。

相关报道

代表稿当事方或官方发布

Endeavour Mining 通报 Mana 金矿通道坡道局部塌陷

Endeavour Mining · 官方动态 · 2026-11-02

Endeavour Mining 通报,10月28日通往已采空的 Wona 露天矿的通道坡道发生局部塌陷,导致布基纳法索 Mana 金矿 Dangouna 和 Aviera 两个井下矿口通道受限,事故未造成人员伤亡,公司随即启动应急预案并疏散全部井下作业人员、通知当地政府。Mana 三个在产井下矿口均已暂停采矿,以便开展岩土工程分析和坡道修复评估;公司称仍有望实现 2026 财年集团产量与 AISC 指引,并正评估通过重启 Wona 矿口及其他近矿露天矿来缓解影响。岩土分析与修复计划详情将于 11 月 12 日发布的 2026 年第三季度业绩中披露。

最新进展当事方或官方发布

Endeavour Mining 通报 Mana 金矿通道坡道局部塌陷

Endeavour Mining · 官方动态 · 2026-11-02

Endeavour Mining 通报,10月28日通往已采空的 Wona 露天矿的通道坡道发生局部塌陷,导致布基纳法索 Mana 金矿 Dangouna 和 Aviera 两个井下矿口通道受限,事故未造成人员伤亡,公司随即启动应急预案并疏散全部井下作业人员、通知当地政府。Mana 三个在产井下矿口均已暂停采矿,以便开展岩土工程分析和坡道修复评估;公司称仍有望实现 2026 财年集团产量与 AISC 指引,并正评估通过重启 Wona 矿口及其他近矿露天矿来缓解影响。岩土分析与修复计划详情将于 11 月 12 日发布的 2026 年第三季度业绩中披露。

内容有误?告诉我们

事件后续

查看完整事件

更多操作