Australian Mining · 行业资讯· Adam Daunt·· 11 天前AI 评分60.0

Capricorn Metals 推进西澳金矿扩建,目标五年内年产 50 万盎司

Capricorn Metals sets course for 500,000oz ambition

本站公开

AI 导读

Capricorn Metals 在 9 月季度按期、按预算完成 Karlawinda 扩建项目建设,达到 650 万吨/年的稳态处理能力,年产量预计从约 12 万盎司提升至 15 万盎司,并维持 2026–27 财年 13.7 万–14.7 万盎司的指引。该季度 Karlawinda 产金 31,218 盎司,全维持成本为 2005 美元/盎司,运营现金流 1.131 亿美元,季末现金及黄金持有量为 5.35 亿美元。Mt Gibson 金矿项目已获联邦环境批准,详细设计与主要合同已完成,更新后的预可行性研究给出 19.25 年矿山寿命,稳态期四年年均产量约 260,900 盎司;公司计划在 Mt Gibson 投产 2.5 年内使合计年产量超过 40 万盎司,并研究在 Golden Range 建设第二个选矿中心,以推进“Range 500”战略。

正文 · 原文

中文译文生成中,先为你显示原文。

查看配图:Capricorn
Image: Victor Moussa/stock.adobe.com

Capricorn Metals is laying the groundwork for a significant expansion of its Western Australian gold operations as it pursues an ambitious target of producing 500,000 ounces annually within five years.

The company completed construction of the Karlawinda Expansion Project on schedule and within budget during the September quarter, achieving its targeted steady-state processing throughput of 6.5 million tonnes per annum.

The expanded operation is expected to lift annual gold production from approximately 120,000 ounces to 150,000 ounces, with Capricorn maintaining its 2026–27 financial year guidance of 137,000–147,000 ounces.

Karlawinda produced 31,218 ounces during the quarter, up from 30,437 ounces in the previous period, at an all-in sustaining cost of $2005 per ounce.

The operation generated $113.1 million in operating cash flow, while Capricorn finished September with $535 million in cash and gold holdings.

Attention is also turning towards the Mt Gibson Gold Project, where detailed engineering is complete and major contracts have been finalised, subject to outstanding approvals.

Capricorn has received federal environmental approval for Mt Gibson and is progressing the remaining Western Australian permitting requirements.

An updated pre-feasibility study outlined a 19.25-year mine life, with average annual production of approximately 260,900 ounces during four years of steady-state operations.

Together, Karlawinda and Mt Gibson are expected to support a production run rate exceeding 400,000 ounces annually within 2.5 years of Mt Gibson commencing operations.

Capricorn is also investigating a second processing hub at Golden Range as part of its broader ‘Range 500’ growth strategy.

“Range 500 is an exciting opportunity for Capricorn to pursue given the significant growth already underway at Karlawinda and development ready at Mt Gibson,” Capricorn Metals executive chairman Mark Clark said in July. 

“With the current medium-term gold production outlook for the combined business now over 400,000 ounces per annum, pursuing growth to 500,000 ounces per annum by optimising Mt Gibson and Golden Range is a significant value creation goal to pursue.

“Achieving this goal has the potential to lift Capricorn into a uniquely attractive position in the Australian mid-tier gold mining space.”

Preliminary study results are expected later in the December quarter, with a pre-feasibility study and final investment decision targeted for 2027.

Meanwhile, exploration at Mt Gibson continues to identify high-grade underground mineralisation, including a 6m intersection at 57.38 grams per tonne gold at Lexington.

The company expects to deliver a maiden underground mineral resource estimate for Lexington during the December quarter.

Subscribe to Australian Mining and receive the latest news on product announcements, industry developments, commodities and more.

Australian Mining.

来源:Australian Mining · 行业资讯 · australianmining.com.au

许可:负责人声明许可;来源异议或指示可逐项收紧