Mako Mining 目标 2028 年实现 Eagle Mountain 金矿首次投产

Mako Mining targets 2028 production at Eagle Mountain gold project

本站公开

AI 导读

加拿大公司 Mako Mining 计划在 2028 年前实现圭亚那第八区 Eagle Mountain 金矿项目首次投产,公司预计未来数月取得关键环境与建设许可。首席执行官 Akiba Leisman 表示,最终环境影响评估(ESIA)有望最早于本日历年获批,进而最早在 2027 年第一季度获得圭亚那政府颁发的完整建设许可。该项目勘探许可证覆盖约 48 平方公里,包含 Eagle Mountain 与 Salbora 两个金矿床,按 2024 年初步经济评估(PEA)规划为 15 年露天金矿,年均产金 66,500 盎司。

正文 · 原文

中文译文生成中,先为你显示原文。

Nov 11, 2026 News


(Kaieteur News) – Canadian company Mako Mining Corporation is targeting first production at its Eagle Mountain gold project in Region Eight (Potaro-Siparuni) by 2028, as the company expecting to secure key environmental and construction permits in the coming months.

The company’s Chief Executive Officer (CEO), Akiba Leisman, disclosed this during an interview with Charlando in English, where he outlined the remaining regulatory requirements and preparatory works ahead for the development of the project.

查看配图:Mako Mining targets 2028 production at Eagle Mountain gold project

Chief Executive Officer (CEO) of Mako Mining, Akiba Leisman.

The Eagle Mountain Gold Project is located in Region Eight (Potaro-Siparuni). The Eagle Mountain Prospecting Licence (EMPL), covers approximately 48 square kilometres (km²). The project has two gold deposits, the Eagle Mountain and Salbora, as well as several other exploration targets.

During the interview, Leisman said Mako submitted its draft Environmental and Social Impact Assessment (ESIA) to the Environmental Protection Agency (EPA) at the end of April and has since received some minor comments from the relevant authorities.

“We’ve gotten some minor comments back on that. So hopefully we can address those and get our final ESIA up and ready and approved as early as this calendar year,” he explained.

He outlined that approval of the final ESIA could pave the way for the company to obtain its full construction permit from the Government of Guyana as early as the first quarter of 2027.

Leisman added that while the permitting process is ongoing, Mako has already begun spending on preliminary construction-related activities in Guyana. He explained that these include engineering work associated with the deposit, as well as repairs to roads and bridges needed to facilitate the transportation of heavy equipment to the project site.

查看配图:Mako Mining targets 2028 production at Eagle Mountain gold project

File photo of development of Eagle Mountain Gold Project.

However, he cautioned that obtaining the necessary permits by March 2027 would not necessarily mean that major construction could begin immediately. The CEO explained that Mako is currently coordinating the development of Eagle Mountain with work at its Mount Hamilton project, which must reach approximately 80% completion before Mako can commit the necessary capacity to undertake major construction at Eagle Mountain.

“So even if we do get this thing fully permitted in March next year, which is theoretically possible, it’s not like we can actually do the major things on this until late Q3 of next year, like around this time regardless,” Leisman said.

In September, Mako announced the execution of a mineral agreement with the Government of Guyana and the Guyana Geology and Mines Commission (GGMC). The agreement provides the company and its 100%-owned subsidiary, Stronghold Guyana Inc., with a stability framework covering legal, fiscal and operating conditions for the Eagle Mountain Gold Project.

The agreement is structured as a mineral agreement under Guyana’s Mining Act and provides legal stability for mining licences, prospecting licences, authorisations as well as fiscal terms for 10 years, subject to specific environmental provisions.

This publication reported the Eagle Mountain project came under the control of Mako Mining following its acquisition of Goldsource Mines Inc. in July 2024. Through the takeover, Mako inherited a Mineral Resource Estimate (MRE) of approximately 1.2 million ounces of gold in the indicated category and 582,000 ounces in the inferred category.

The project is planned for an open pit gold mine over a 15-year period and is expected to produce 66,500 ounces of gold annually – according to a 2024 Preliminary Economic Assessment (PEA).


Discover more from Kaieteur News

Subscribe to get the latest posts sent to your email.



来源:Kaieteur News—RSS · kaieteurnewsonline.com

许可:负责人声明许可;来源异议或指示可逐项收紧

原始来源可追溯;中文内容由 AI 辅助生成或翻译,核对细节请看原文。

内容有误?告诉我们

事件后续

查看完整事件

更多操作