Hudbay与三菱批准21亿美元Copper World铜矿项目建设

Hudbay, Mitsubishi approve Copper World construction

Public on this site

AI summary

Hudbay Minerals与日本三菱批准美国亚利桑那州南部Copper World铜矿项目开工建设,资本开支21亿美元(29亿加元),较2023年预可行性研究的13亿美元估算上升59%,其中因范围调整增加2亿美元。Hudbay预计出资约5亿美元,不足初始投资四分之一,首期款项推迟至2028年。项目在完成最终可行性研究(DFS)后获批,预计2029年下半年投产,有望将Hudbay合并年铜产量提升至约25万吨。

Text · original

The Chinese translation is being made; the original is shown for now.

查看配图:Hudbay Copper World
Workers on the Copper World project site. Credit: Hudbay Minerals.

Hudbay Minerals (TSX, NYSE: HBM) and Japan’s Mitsubishi have approved construction of the $2.1-billion (C$2.9 billion) Copper World project in southern Arizona despite a 59% surge in construction costs.

Scope changes since a 2023 prefeasibility study have resulted in $200 million of additional capital costs, Hudbay said Wednesday in a statement. Hudbay expects to contribute about $500 million, less than one-quarter of the initial investment, with its first installment deferred until 2028. Capital costs were previously estimated at $1.3 billion in the 2023 study.

“The Copper World sanction decision is a positive step towards Hudbay’s medium term growth plans, although the share price reaction may be limited as the scope of the project and initial capex estimates are largely as expected,” RBC Capital Markets mining analyst Sam Crittenden said Wednesday in a note.

The move, which follows the completion of a definitive feasibility study (DFS), clears the way for one of the largest new copper mines in the United States to start producing in the second half of 2029. Copper World, located about 50 km southeast of Tucson, is expected to help double Hudbay’s consolidated annual copper production to about 250,000 tonnes, alongside growth initiatives at the company’s existing operations.

Hudbay shares rose 0.2% to C$33.34 Wednesday morning in Toronto, valuing the company at about C$14.8 billion ($10.6 billion). The stock has traded between C$20.26 and C$44.48 in the past year.

Source: Canadian Mining Journal · 行业资讯 · canadianminingjournal.com

Licence: 负责人声明许可;来源异议或指示可逐项收紧

The original source is traceable; the Chinese content is written or translated with AI assistance ; check the original for details.

Related coverage

Representative report

Hudbay 与三菱批准美国 Copper World 铜矿项目建设

Revista ProActivo · 行业资讯 · 2026-10-22 02:39

Hudbay 与三菱已正式作出最终投资决定,推进位于美国亚利桑那州、距 Tucson 东南约 50 公里的 Copper World 铜矿项目建设,预计 2029 年下半年投产。Hudbay 持股 70%、三菱持股 30%;最终可行性研究预计前 10 年年均产铜 102,000 吨,较 2023 年预可行性研究的 92,000 吨提高 11%,前 10 年平均 C1 现金成本为 1.65 美元/磅。初始增长资本估计为 20.70 亿美元,扣除贵金属产品流协议预付款后为 18.40 亿美元;融资包括三菱 6 亿美元初始股权投资、Wheaton Precious Metals 2.30 亿美元预付款及约 6.50 亿美元项目级债务融资。项目证实及可信储量 3.90 亿吨、铜品位 0.47%,选矿厂初始处理能力 60,000 吨/日,计划第五年扩至 90,000 吨/日。

Latest

Hudbay 与三菱批准美国 Copper World 铜矿项目建设

Revista ProActivo · 行业资讯 · 2026-10-22 02:39

Hudbay 与三菱已正式作出最终投资决定,推进位于美国亚利桑那州、距 Tucson 东南约 50 公里的 Copper World 铜矿项目建设,预计 2029 年下半年投产。Hudbay 持股 70%、三菱持股 30%;最终可行性研究预计前 10 年年均产铜 102,000 吨,较 2023 年预可行性研究的 92,000 吨提高 11%,前 10 年平均 C1 现金成本为 1.65 美元/磅。初始增长资本估计为 20.70 亿美元,扣除贵金属产品流协议预付款后为 18.40 亿美元;融资包括三菱 6 亿美元初始股权投资、Wheaton Precious Metals 2.30 亿美元预付款及约 6.50 亿美元项目级债务融资。项目证实及可信储量 3.90 亿吨、铜品位 0.47%,选矿厂初始处理能力 60,000 吨/日,计划第五年扩至 90,000 吨/日。