Lindian Resources 的马拉维 Kangankunde 稀土项目推进至调试阶段

Lindian’s Kangankunde rare earths project advances towards commissioning

Public on this site

AI summary

Lindian Resources 通报马拉维 Kangankunde 稀土项目建设、采矿与调试准备进展,目标在 2026 年 12 月产出首批独居石精矿。

Text · original

The Chinese translation is being made; the original is shown for now.

查看配图:Kangankunde Process Plant. Photo: Lindian Resources

Kangankunde Process Plant. Photo: Lindian Resources

Published by

Lindian Resources Limited announces an update on construction, mining activities and commissioning readiness at its Kangankunde Rare Earths Project in Malawi, as construction advances towards commissioning and first monazite concentrate production in December 2026. With key processing equipment installed, electrical works progressing and ore inventories growing, the Project remains on schedule for first production.

Highlights:

  • First monazite concentrate on target for December 2026, with construction and operational readiness activities advancing towards commissioning.
  • Ore stockpiles increased to approximately 149,000 tonnes*, up approximately 24,000 tonnes, or 19%, from September 2026.
  • Key power milestones achieved, with the 33kV overhead line commissioned to the transformer yard and both 1,250 kVA plant transformers returned to site following successful factory acceptance testing. Site energisation is targeted for the first week of November 2026.
  • Separation circuits taking shape, with structural steel in the WHIMS and MGS areas approximately 90% complete and shaking tables approximately 80% complete. Installation of the regrind mill is complete.
  • Transition to operations under way, with initial operating personnel on board, operator training commenced and outbound concentrate logistics contracts nearing finalisation.

Lindian's Executive Director, Zac Komur, commented: "Kangankunde is in the final stretch of construction. Our target is clear: first monazite concentrate in December. The plant is taking shape, ore stockpiles are growing and our focus is on completing the remaining work and commissioning safely. Every milestone brings us closer to becoming a rare earths producer."

* The ore stockpile tonnage is derived from the existing Ore Reserve estimates.

Newsletter

Get the latest news straight to your inbox. (Free of charge)

Source: MININGMETALnews · 行业资讯 · miningmetalnews.com

Licence: 负责人声明许可;来源异议或指示可逐项收紧

The original source is traceable; the Chinese content is written or translated with AI assistance ; check the original for details.

Related coverage

Representative reportReading now

Lindian Resources 的马拉维 Kangankunde 稀土项目推进至调试阶段

MININGMETALnews · 行业资讯 · 2026-10-16

Lindian Resources 通报马拉维 Kangankunde 稀土项目建设、采矿与调试准备进展,目标在 2026 年 12 月产出首批独居石精矿。

LatestReading now

Lindian Resources 的马拉维 Kangankunde 稀土项目推进至调试阶段

MININGMETALnews · 行业资讯 · 2026-10-16

Lindian Resources 通报马拉维 Kangankunde 稀土项目建设、采矿与调试准备进展,目标在 2026 年 12 月产出首批独居石精矿。

Something wrong? Tell us

Event follow-ups

See the full event

More actions