Tanami Gold与MGX完成Groundrush金矿两条井口爆破,推进地下开发

Groundrush takes major step towards underground development

Public on this site

AI summary

Tanami Gold与MGX Resources已完成北领地Groundrush金矿中央与通风井口的爆破,这是Central Tanami项目合资企业(CTPJV)迈向2027年开发决策的重要节点。该里程碑属于Macmahon Underground于8月获得的3800万美元合同,涵盖两条井口建设及初期3.5km勘探斜坡道施工,斜坡道预计14个月建成、深度约350m。斜坡道建成后将支撑约33000m加密钻探,目标是把Groundrush超过40万盎司推断金资源量转为控制类别;Groundrush资源量为1100万吨、品位3.3g/t、约120万盎司。

Text · original

The Chinese translation is being made; the original is shown for now.

Source: Australian Mining · 行业资讯 · australianmining.com.au

Licence: 负责人声明许可;来源异议或指示可逐项收紧

The original source is traceable; the Chinese content is written or translated with AI assistance ; check the original for details.

Related coverage

Representative report

MGX 启动 Central Tanami 金矿 Groundrush 斜坡道施工

Australian Mining · 行业资讯 · 2026-10-30 07:55

MGX Resources 在 9 月季度报告中确认,Macmahon Underground 已进驻北领地 Central Tanami 项目现场,开始建设 Groundrush 斜坡道。该工程基于 8 月授予的 3800 万美元施工合同,为期 14 个月,将完成首段 3.5km 地下斜坡道开拓,为资源圈定钻探提供通道。地下钻探计划于 2027 年启动,约 33,000m,目标是推动超过 40 万盎司推断金资源量升级为控制类别。MGX 与 Tanami Gold 各持该项目合资公司 50% 权益,项目矿产资源量为 280 万盎司,MGX 权益份额为 140 万盎司。同期,MGX 已于 7 月完成 Koolan Island 最后一批低品位铁矿石发运,结束近二十年的生产,并计划在 2026 年底或 2027 年初将该项目出售给 Crestlink。季度末公司现金及投资储备为 4.087 亿美元,无银行借款。

LatestReading now

Tanami Gold与MGX完成Groundrush金矿两条井口爆破,推进地下开发

Australian Mining · 行业资讯 · 2026-11-12 08:06

Tanami Gold与MGX Resources已完成北领地Groundrush金矿中央与通风井口的爆破,这是Central Tanami项目合资企业(CTPJV)迈向2027年开发决策的重要节点。该里程碑属于Macmahon Underground于8月获得的3800万美元合同,涵盖两条井口建设及初期3.5km勘探斜坡道施工,斜坡道预计14个月建成、深度约350m。斜坡道建成后将支撑约33000m加密钻探,目标是把Groundrush超过40万盎司推断金资源量转为控制类别;Groundrush资源量为1100万吨、品位3.3g/t、约120万盎司。