Ramelius Resources has begun building the processing capacity required for its next production leap within its portfolio.

The gold producer is targeting annual output of more than 600,000 ounces by the 2030 financial year (FY30), supported by an expansion of its Mount Magnet processing hub and the development of the Rebecca–Roe project.

Ramelius awarded Primero an engineering, procurement and construction contract for a new three-million-tonne-per-annum Circuit 2 at Mount Magnet. The additional circuit will operate alongside the existing two-million-tonne-per-annum plant, lifting total installed processing capacity to approximately five million tonnes per annum.

Stage 1 works also progressed during the September quarter, with a new crusher and gravity tower integrated into the existing processing circuit.

The investment comes as Ramelius strengthens its financial position following the $300 million sale of Edna May to Forrestania Resources. The consideration comprised $210 million in cash and $90 million in Forrestania shares. Ramelius ended the quarter with $768 million in cash and gold.

Ramelius produced 48,839oz of gold at an all-in sustaining cost of $2656/oz during the quarter. Wet weather interrupted haulage from the high-grade Penny mine, leaving ore stockpiled for processing in the December quarter, but the company maintained its FY27 guidance of 205,000–225,000oz at an AISC of $2150–2350/oz.

Progress also occurred at Rebecca–Roe, where the Department of Water and Environmental Regulation granted a Part V works approval for Roe and the associated mining approvals are being pursued.

Ramelius managing director Mark Zeptner said the company was advancing its longer-term production strategy.

“We are systematically de-risking our business plan to become a 600,000-ounce producer by FY30,” he said.

“We are executing on our business plan to deliver real value to our shareholders.”

Subscribe to Australian Mining and receive the latest news on product announcements, industry developments, commodities and more. 

Australian Mining.

Source: Australian Mining · 行业资讯 · australianmining.com.au

Licence: 负责人声明许可;来源异议或指示可逐项收紧

The original source is traceable; the Chinese content is written or translated with AI assistance ; check the original for details.

Related coverage

Representative reportReading now

Ramelius Resources 启动扩建,目标 FY30 年产金超 60 万盎司

Australian Mining · 行业资讯 · 2026-10-26 08:02

Ramelius Resources 已启动为下一轮产量增长所需的加工产能建设,目标在 2030 财年(FY30)实现年产金超过 60 万盎司。公司把 Mount Magnet 新增年处理 300 万吨的 Circuit 2 的工程、采购和施工合同授予 Primero,该回路将与现有年处理 200 万吨的工厂并行运行,使总装机加工能力提升至约每年 500 万吨。本季度公司产金 48,839 盎司,全维持成本为 2656 澳元/盎司,并维持 FY27 产量指引 205,000–225,000 盎司、AISC 2150–2350 澳元/盎司。

Latest

Ramelius 启动西澳 Eridanus 金矿第三期露天扩帮

Australian Mining · 行业资讯 · 2026-11-04 08:18

Ramelius Resources 已启动西澳 Eridanus 金矿床第三期露天扩帮,为 Mt Magnet 选矿中心提供后续矿石来源。Eridanus 按 2025 年 6 月估算拥有约 3000 万吨、品位 1.6 g/t 金、含金 150 万盎司的资源量,该矿床于 2017 年被发现,一期露天矿于 2019 年中投产、二期于 2020 年 6 月跟进。此次扩帮服务于公司到 FY30 实现年产金超过 60 万盎司的目标,Mt Magnet 同时由 Primero 承建年处理 300 万吨的新选矿回路,与现有 200 万吨/年工厂并行后总产能约 500 万吨/年。

Something wrong? Tell us

Event follow-ups

See the full event

More actions