Allied Gold Advances Wet Commissioning at Kurmuk as Plant Nears First Gold, Ethiopia

Public on this site

AI summary

Allied Gold表示,埃塞俄比亚Kurmuk矿已开始湿法调试,目标在11月和12月产出2.5万至3.5万盎司黄金,并在此期间实现商业化生产。公司预计2027年产量为24万至27万盎司,2028年约30万盎司;矿石预计本周进入选矿流程,随后产出首批黄金。矿山及选厂基础设施已完工,包括蓄水与尾矿设施、主通道和采矿服务区,矿石堆存接近约三个月给矿量的计划水平。

Why it matters

原文列出Kurmuk矿湿法调试、投产时间与2027至2028年产量指引,可据此了解项目进度。

Published: November 2, 2026 |

Allied Gold Corporation said it has begun wet commissioning at Ethiopia’s Kurmuk Mine, targeting 25,000 to 35,000 gold ounces in November and December. Allied expects commercial production during that period, ahead of 240,000 to 270,000 ounces forecast for 2027.

Allied said water transfer into the processing plant has started, allowing circuits to be wet-commissioned before ore feed. The grinding mill drives are energized, with testing and commissioning nearing completion.

“Ore is expected to be introduced into the circuit this week with first gold targeted soon thereafter,” Allied said in the release.

The crushing circuit is operating and the crushed ore stockpile continues to grow. Mine and plant infrastructure is complete, including the water storage and tailings facilities, main access road and mining service areas.

Ore stockpiles are close to the planned level of approximately three months of plant feed ahead of the November ramp-up, Allied said. Mining grades are in line with expectations, providing feed for the transition from commissioning to commercial production.

The company had reported the first ore through the crushing circuit on Sept. 17, when it also confirmed that the mine’s connection to Ethiopia’s electrical grid had been commissioned and energized. The Sept. 17 release put the fixed power tariff at approximately $0.04 per kilowatt-hour under a 20-year purchase agreement.

Kurmuk’s first-quarter production is forecast at 55,000 to 65,000 ounces in 2027, with output increasing month by month. Allied expects approximately 300,000 ounces in 2028 and average annual production of about that level over the first four full years.

The startup has moved beyond the August timing anticipated in Allied’s Aug. 5 results, which expected first gold a few weeks after operations began. That release cited prior partial-year production guidance of 100,000 to 150,000 ounces for Kurmuk.

The August results also said Allied expected cash balances to increase through the remainder of 2026 as Kurmuk development spending declined and production began.

Allied also said it has reached an agreement with local stakeholders, including artisanal miners active in parts of its exploration licenses, to explore new prospective areas cooperatively. It links that access and ongoing exploration to its objective of sustaining approximately 300,000 ounces annually beyond the first four years.

Allied is a Canadian-based gold producer with operating mines in Mali and Côte d’Ivoire and the Kurmuk development in Ethiopia.

Source: Mugglehead


Allied Gold is a Canadian-based gold producer with a significant growth profile and mineral endowment which operates a portfolio of three producing assets and development projects located in Côte d’Ivoire, Mali, and Ethiopia. Led by a team of mining executives with operational and development experience and proven success in creating value, Allied Gold aspires to become a next-generation mid-tier gold producer in Africa and ultimately a leading senior global gold producer.


Be in-the-know when you’re on-the-go!

FREE eNews delivery service to your email twice-weekly. With a focus on lead-driven news, our news service will help you develop new business contacts on an on-going basis.

CLICK HERE to register your email address.

Source: Mining Connection · 行业资讯 · miningconnection.com

Licence: 负责人声明许可;来源异议或指示可逐项收紧

The original source is traceable; the Chinese content is written or translated with AI assistance ; check the original for details.

Related coverage

Representative reportReading now

Allied Gold埃塞俄比亚Kurmuk矿启动湿法调试,目标近期产出首批黄金

Mining Connection · 行业资讯 · 2026-11-02

Allied Gold表示,埃塞俄比亚Kurmuk矿已开始湿法调试,目标在11月和12月产出2.5万至3.5万盎司黄金,并在此期间实现商业化生产。公司预计2027年产量为24万至27万盎司,2028年约30万盎司;矿石预计本周进入选矿流程,随后产出首批黄金。矿山及选厂基础设施已完工,包括蓄水与尾矿设施、主通道和采矿服务区,矿石堆存接近约三个月给矿量的计划水平。

Latest

Allied Gold拟派息并回购股份,季度经营现金流降至1230万美元

Miningmx · 行业资讯 · 2026-11-06 16:47

Allied Gold计划推出股息和股份回购计划,拟自2027年起派发基础股息,并回购最多占公众流通股10%的股份,尚待多伦多证券交易所批准。9月季度经营现金流入降至1230万美元,上年同期为1.821亿美元;全维持成本上升14%至2378美元/盎司,黄金产量增长5%至91195盎司。埃塞俄比亚Kurmuk新矿已投产,预计今年贡献2.5万至3.5万盎司,2027年增至24万至27万盎司。

Something wrong? Tell us

Event follow-ups

See the full event

More actions