New Pacific Metals · 官方动态· Amal Arrouba·· 2026-07-16PicksAI score62.0

New Pacific Metals公布Carangas更新版初步经济评估:税后净现值26.5亿美元、内部收益率35.9%

New Pacific Metals Reports Results of Updated Carangas Preliminary Economic Assessment: Post-tax $2.65 Billion NPV (5%) and 35.9% IRR; 339.0 Million Oz of Silver Equivalent Produced

Public on this site

AI summary

New Pacific Metals公布玻利维亚Oruro省Carangas项目更新版NI 43-101初步经济评估,按银45.00美元/盎司、金3400美元/盎司、锌1.20美元/磅、铅0.90美元/磅的基准价格,税后净现值(5%)为26.5亿美元,内部收益率35.9%。

Why it matters

原文给出更新版PEA的税后净现值、内部收益率与分阶段产量安排,可据此了解Carangas项目的经济测算口径。

Text · AI translation

The translation is incomplete; switch to the original for the full text.

下载 PDF 版本

不列颠哥伦比亚省温哥华 – 2026年7月16日 – New Pacific Metals Corp.(TSX: NUAG)(NYSE-A: NEWP)(“New Pacific”或“公司”)欣然报告其更新的初步经济评估技术报告的成果,该报告题为“Carangas项目NI 43-101技术报告及初步经济评估”(“更新版Carangas PEA技术报告”),针对位于玻利维亚奥鲁罗省的Carangas项目(“项目”),由Ausenco Engineering Canada ULC(“Ausenco”)依据National Instrument 43-101 – 矿业项目披露标准(“NI 43-101”)编制,生效日期为2026年7月16日。与日期为2024年9月5日的先前初步经济评估技术报告相比,更新版Carangas PEA技术报告考虑了提高的吞吐量以及纳入金矿区。更新版Carangas PEA技术报告的要点如下(所有数字均以美元计):

  • 按基准金属价格:白银(“Ag”)45.00美元/盎司(“oz”)、黄金(“Au”)3,400美元/盎司、锌(“Zn”)1.20美元/磅(“lb”)、铅(“Pb”)0.90美元/磅计算,税后净现值(“NPV”)(5%)为26.5亿美元,内部收益率(“IRR”)为35.9%;
    • 在Ag价格为67.50美元/盎司、其他金属价格保持不变的情况下,税后NPV和IRR分别为41.6亿美元和51.5%;
    • 在Au价格为5,100美元/盎司、其他金属价格保持不变的情况下,税后NPV和IRR分别为32.3亿美元和37.0%; 
  • 矿山寿命(“LOM”)19年,不包括两年建设期,生产约1.95亿盎司(“Moz”)应付Ag、110万盎司应付Au、14.53亿磅(“Mlbs”)应付Zn和9.41亿磅应付Pb,或3.39亿盎司银当量(“AgEq”[1]);
    • 采矿将在第1至第16年进行。第17至第19年,所有产量将来自矿石堆存;
    • 在第1至第8年(“黄金生产前期”),应付白银产量约为每年1550万盎司(每年1890万盎司AgEq);黄金生产前期的平均全维持成本(“AISC”)为18.25美元/盎司AgEq,或扣除副产品后的平均AISC为12.11美元/盎司Ag;
    • 在第9至第16年(“黄金生产期”),应付白银产量约为每年760万盎司,应付黄金产量约为每年14.27万盎司(“koz”)(每年2070万盎司AgEq);黄金生产期的平均AISC为17.78美元/盎司AgEq,或扣除副产品后的平均AISC为-39.49美元/盎司Ag;
    • 第17至第19年(“矿石堆存期”)的应付白银总产量为1030万盎司(2160万盎司AgEq);以及
    • 矿山寿命平均AISC为19.16美元/盎司AgEq,或扣除副产品后的矿山寿命平均AISC为0.11美元/盎司Ag。
  • 初始资本成本为6.445亿美元,税后投资回收期为2.4年。
    • 矿山全生命周期(LOM)资本支出为12亿美元,其中包括4.227亿美元的增长资本支出和1.665亿美元的维持资本支出;以及
    • 关闭成本为1.498亿美元。

该项目具有稳健的经济性、可控的前期资本开支,每年白银产量约一千万盎司,矿山全生命周期内黄金产量超过一百万盎司。随着更新后的Carangas PEA技术报告的完成,公司将推进技术工作,包括一项30,000米的加密钻探计划。除技术工作外,公司还将重点推进项目的许可审批工作,目标是在今年剩余时间内完成勘探许可证(“ELs”)向行政采矿合同(“AMCs”)的转换,并启动环境影响评估研究(“EEIA”)流程。 

经济结果与敏感性分析

表1列出了关键假设,并汇总了更新后的Carangas PEA技术报告的预计产量和经济结果。表2和表3显示了对白银和黄金价格的敏感性,表4显示了对运营和资本成本的敏感性。

[1] AgEq 的计算方式为:AgEq 盎司 = Ag 盎司 + Au 盎司 ×(Au 价格/Ag 价格)+ Zn 磅 ×(Zn 价格/Ag 价格)+ Pb 磅 ×(Pb 价格/Ag 价格),金属价格见表 1

查看配图 查看配图

注释

  1. 矿山寿命期平均剥采比。
  2. 矿山寿命期平均银矿区。
  3. 不含投产前2年期间。
  4. 包括采矿成本、加工成本、尾矿成本、一般及行政(“G&A”)成本、权利金和销售成本。
  5. 包括总运营成本、权利金、维持性资本成本和关闭成本。
  6. 不包括 1.498 亿美元的矿山关闭成本。
  7. 投资回收期从建设完成并开始生产之日起计算。

查看配图

查看配图

资本与运营成本

根据《更新版Carangas PEA技术报告》所述,该项目预计将包括合同采矿露天作业,向常规破碎、磨矿和浮选回路供应磨矿给料,预计生产银铅精矿和锌精矿。预计该作业将在第6年通过增加一套双联破碎、磨矿和浮选回路,从每年800万吨(“Mtpa”)扩大到1600万吨/年。预计在第9年,一套800万吨/年的黄金回路(包括氰化浸出、逆流倾析、Merril-Crowe和冶炼)将投入运行。该回路将利用第二座选矿厂的破碎、磨矿和粗选浮选装置。预计初始选矿厂将继续以800万吨/年的产能运行,生产银铅精矿和锌精矿。《更新版Carangas PEA技术报告》预计该项目将具有多项资本和运营成本优势:

  • 矿化材料呈水平层状,预计将形成一个最终深度约520米的露天采坑(地表以下),全生命周期平均剥采比低至1.4:1;
  • 建议由一家目前在玻利维亚有运营的承包商运营该矿山,从而无需公司采购采矿车队并为车队更换持续投入资本;
  • 邦德球磨功指数(BBWi)平均为12千瓦时/公吨(“kWh/t”),邦德磨蚀指数(Ai)平均为0.06,因此预计处理矿化物料将需要适度的电力消耗和较低的研磨介质消耗;
  • 试验工作表明,银/铅精矿和锌精矿中的总银回收率良好,平均为83.9%,其中银/铅精矿的银品位较高,预计在第3至第9年将超过3,500克/吨(“g/t”);预计该矿山将接入国家电网,为选矿厂及其他现场基础设施提供0.06美元/千瓦时的低成本电力;以及
  • 该矿区可通过国道和全天候地方道路进入。

查看配图

查看配图

注意

  1. 包括5500万美元的投产前资本化运营成本。
  2. 包括土方工程、电力开关站及配电、燃料储存、污水、饮用水、水管理、基础设施建筑、尾矿储存设施、尾矿及回采管道、营地,以及现场服务和移动设备。
  3. 包括进场道路、供水、输电线路和城镇搬迁。
  4. 扩建资本成本包括第6年选矿厂的复制扩建以及第9年新增黄金工厂。
  5. 维持性资本成本包括采矿和尾矿成本。

采矿

预计该矿床将采用常规露天开采方式进行开采。这包括钻孔和爆破,使用液压挖掘机装载,并由非公路后卸式自卸卡车运输。图1展示了显示资源模型品位和采场的西南-东北向剖面图。图2展示了矿山生产计划。

选矿厂给矿吨位和品位是矿产资源估算(“MRE”)的子集,已计入计划采矿贫化和回收率。采用13.50美元/吨的采矿净冶炼厂收益(“NSR”)边界品位,所有低于该边界品位的开采物料均作为废石处理。选择该采矿边界品位是为了覆盖项目的选矿及一般与行政(G&A)运营成本。

更新后的Carangas PEA技术报告假设,选矿厂给矿将被运输至主破碎机或破碎机附近的原矿(“ROM”)堆场。早期开采的部分氧化物和低品位资源计划堆存于露天采场以东,并在矿山服务期内进行加工。废石将被运输至露天采场以北的废石储存设施,或用于在露天采场更北处建造尾矿储存设施坝体。预计矿山运营将由一家目前在玻利维亚有运营业务的承包商承担。

预计露天采矿将在建设的第一年启动。矿山计划预计,在为期两年的生产准备期内将开采 19 Mt 废石和氧化物料。露天矿峰值产量预计为每年 85 Mt。计划中的露天矿共含有 615 Mt 物料(矿化物料和废石),计划在选矿运营的第 16 年开采完毕。计划在整个矿山寿命期内将 105 Mt 氧化物料和低品位物料堆存,第 16 至 19 年将仅处理堆存物料。堆存的氧化物料将在整个矿山寿命期内被重新倒运至选矿厂,目标是占银矿区选矿给矿总量的 13%。

查看配图

说明:净冶炼厂价格(“NSP”)和冶金回收率用于确定NSR截止品位。NSP包含的市场价格假设为:银40.0美元/盎司、金3,200美元/盎司、铅0.90美元/磅、锌1.20美元/磅。各项冶炼和精炼条款、场外成本以及5%的权利金(银为6%)得出NSP为:锌精矿中银17.5美元/盎司、铅精矿中银34.4美元/盎司、合质金中银34.8美元/盎司、合质金中金3,028美元/盎司、铅1,070美元/吨、锌1,270美元/吨。采用的冶金回收率为:锌精矿中银6%、铅精矿中银81.6%、合质金中银60.4%、合质金中金93.4%、锌精矿中铅2.3%、铅精矿中铅73.4%、锌精矿中锌66.9%、铅精矿中锌21.9%。经济分析所用的金属价格、冶炼条款和回收率与本处所述数值略有不同。合格人员已进行核查,以确保将这些投入修订为用于评估《更新版Carangas PEA技术报告》中项目经济性的金属价格后,矿山计划不会发生重大改变。

查看配图

选矿

该项目设计在前5年处理8.0百万吨/年的矿化物料,在第6至18年处理16.0百万吨/年。整体选厂生产计划如图3所示。加工设施将采用常规破碎磨矿回路,随后进行选择性顺序浮选,以生产铅/银精矿和锌/银精矿。这些回路将包括一段破碎,随后是SAG-球磨回路和顺序选择性浮选,以分离银/铅和锌,同时排除黄铁矿和非硫化物脉石矿物。 在第9至16年,金厂将对金浮选精矿采用常规氰化浸出,并结合CCD、Merrill Crowe和冶炼回路生产金锭。尾矿随后将被浓缩并泵送至常规储存设施。

查看配图

矿产资源量估算

该矿产资源量估算(MRE)为报告目的采用概念性露天采坑壳进行约束,以30 g/t AgEq的边界品位报告,并在表6中列示,生效日期为2026年3月31日。

查看配图

后续步骤

更新后的 Carangas PEA 技术报告所展现的强劲经济性,支持 New Pacific 继续推进该项目的技术和许可方面工作。近期在与当地社区方面已取得进展,包括今年早些时候签署了一项社区框架协议(见 2026 年 2 月 23 日的新闻稿),以及在 7 月 6 日成功完成了一次事先磋商,以获得社区及其他区域利益相关方的同意,这是将 Carangas ELs 转换为 AMCs 的要求之一。ELs 转换为 AMCs 的申请流程始于 2025 年,此后所有所需文件均已提交至玻利维亚矿业和冶金部。  随着近期事先磋商的完成,公司预计 ELs 转换为 AMCs 的剩余行政工作和立法批准可能需要长达六个月的时间。

随着在取得AMC方面取得的进展,公司计划于2026年9月在Carangas启动一项30,000米的钻探活动。约25,000米钻探将侧重于将推断资源量转换为指示资源量,其余钻探将测试Carangas金矿区的可能延伸和新外推目标。作为这项工作的一部分,公司还将采集用于可行性级别冶金测试的样品,并开展岩土和水文钻探。

取得AMC后,公司将开始向玻利维亚环境与水资源部申请将其拟建露天开采项目进行环境分类,从而正式启动EEIA程序。 同时还将开始收集环境和社会基线数据以及其他相关技术工作,以满足EEIA的要求。预计这项工作将于2027年底前完成。

合资格人士

更新版 Carangas PEA 技术报告的合资格人士为:SLR 首席地质师 Anderson Candido 先生(FAusIMM)、JJ Metallurgical Services 冶金师 Jinxing Ji 先生(P.Eng.)、Ausenco Engineering Canada ULC(“Ausenco”)首席工艺工程师 Kevin Murray 先生(P.Eng.)、Ausenco 全球技术负责人(岩土工程)Scott Elfen 先生(PE、SME)、Ausenco 战略项目总监 James Millard 先生(P.Geo.),以及 Moose Mountain Technical Services 采矿工程师 Marc Schulte 先生(P.Eng.)。每位合资格人士所负责的具体章节将在更新版 Carangas PEA 技术报告中列明。所有上述合资格人士均已审阅并核实本新闻稿中与其所负责的更新版 Carangas PEA 技术报告章节相关的技术内容。合资格人士已核实报告中其负责章节所披露的信息。

更多细节(包括风险和不确定性)将纳入更新后的 Carangas PEA 技术报告,该报告将在本新闻稿发布后 45 天内发布在公司于 sedarplus.com 上的公司简介下。

本新闻稿已由 New Pacific Metals Corp. 勘探副总裁、注册地质师 Alex Zhang 审阅并批准,其为公司指定的合格人员。

关于新太平洋金属公司(New Pacific Metals)

New Pacific是一家加拿大勘探与开发公司,正在推进玻利维亚两个处于许可阶段贵金属项目。其位于Potosí的Silver Sand项目有潜力成为全球最大的银矿之一。位于Oruro的Carangas银金项目通过规模、稳健的经济性和区域勘探潜力增强了公司的项目组合。凭借在玻利维亚近十年的运营经验,New Pacific已赢得利益相关方和股东的信任。

更多信息

Peter Lekich,投资者关系与企业发展总监

电话:(604) 633‐1368 分机 223,
美国及加拿大免费电话:1-877-631-0593
电子邮件:plekich@newpacificmetals.com

如需了解更多信息并通过电子邮件接收公司新闻,请使用 New Pacific 的网站 www.newpacificmetals.com 进行注册。

关于初步经济评估结果的警示性说明

The results of the Preliminary Economic Assessment prepared in accordance with NI 43-101 titled “Carangas Project NI 43-101 Technical Report and Preliminary Economic Assessment” with an anticipated effective date of July 16, 2026 and prepared by certain qualified persons are preliminary in nature and are intended to provide an initial assessment of the Project’s economic potential and development options. The Updated Carangas PEA Technical Report mine schedule and economic assessment includes numerous assumptions and is based on both indicated and Inferred Mineral Resources. Inferred resources are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves, and there is no certainty that the preliminary economic assessments described herein will be achieved or that the Updated Carangas PEA Technical Report results will be realized. The estimate of Mineral Resources may be materially affected by geology, environmental, permitting, legal, title, socio-political, marketing or other relevant issues. Bolivia has recently experienced significant social unrest, including protests and blockades that led to a government-declared state of emergency. The Company’s projects have also previously been affected by illegal artisanal and small-scale mining activity, which resulted in disruption to operations. Such political and social instability could adversely affect the assumptions underlying the Updated Carangas PEA Technical Report, including anticipated permitting timelines, construction schedules, and operating costs. Mineral resources are not Mineral Reserves and do not have demonstrated economic viability. Additional exploration will be required to potentially upgrade the classification of the Inferred Mineral Resources to be considered in future advanced studies.  The pit design for the deeper gold zone requires mining of waste (waste stripping) on Mining Concessions in the southern portion of the planned open pit that do not belong to the Company. These concessions include approximately 1.85% of the mineral resources that have been included in the economic analysis for this PEA. These Concessions are held by the state of Bolivia and are not currently available for tenure. Although the Company is actively working with the Bolivian government to obtain them, failure to do so, or to enter into a mining agreement on them could cause the Company to reevaluate the pit design and the outcome of this PEA. Ausenco Engineering Canada ULC (“Ausenco”) (Processing Plant, Infrastructure, Tailings, Water Management, Environment, Cost Estimate) was contracted to lead the PEA in cooperation with SLR Canada (minerals resources), Moose Mountain Technical Services (mining), and JJ Metallurgical Services (Metallurgy). The qualified persons for the Updated Carangas PEA Technical Report are Mr. Anderson Candido, FAusIMM, Principal Geologist with SLR Mr. Jinxing Ji, P.Eng., Metallurgist with JJ Metallurgical Services, Mr. Kevin Murray, P.Eng., Principle Process Engineer with Ausenco, Mr. Scott Elfen, PE, SME, and Global Technical Lead (Geotechnical) with Ausenco, Mr. James Millard, P. Geo., Director, Strategic Projects with Ausenco, and Mr. Marc Schulte, P.Eng., Mining Engineer with Moose Mountain Technical Services. All qualified persons for the Updated Carangas PEA Technical Report have reviewed and verified the disclosure of the Updated Carangas PEA Technical Report herein. The mineral resource estimate contained in the Updated Carangas PEA Technical Report is based on the MRE  with an effective date of August 25, 2023, with a re-statement on March 31, 2026. Mineral Resources are constrained by an optimized pit shell at a metal price of $41.00/oz Ag, $3,300.00/oz Au, $1.00/lb Pb, $1.30/lb Zn, $4.00/lb Cu, recovery of 81.6% Ag, 93.4% Au, 73.4% Pb, 66.9% Zn, 38.7% Cu and Cut-off grade of 30 g/t AgEq. Assumptions made to derive a cut-off grade included mining costs, processing costs, and recoveries were obtained from comparable industry situations.

关于前瞻性信息的警示性说明

本新闻稿中的某些陈述和信息构成1995年《美国私人证券诉讼改革法案》所指的“前瞻性陈述”,以及适用的加拿大省级证券法所指的“前瞻性信息”。任何表达或涉及有关预测、预期、信念、计划、推测、目标、假设或未来事件或业绩的讨论的陈述或信息(通常但不总是使用“预期”、“预计”、“预料”、“相信”、“计划”、“推测”、“估计”、“假设”、“打算”、“战略”、“目标”、“目的”、“预测”、“指标”、“预算”、“时间表”、“潜力”等词语或短语或其变体,或声明某些行动、事件或结果“可能”、“能够”、“将会”、“或许”或“将”被采取、发生或实现,或任何这些术语和类似表述的否定形式)均不是对历史事实的陈述,且可能属于前瞻性陈述或信息。此类陈述包括但不限于关于以下内容的陈述:更新后的Carangas PEA技术报告的结果以及更新后的Carangas PEA技术报告的提交时间;对项目的预期;关于净现值、矿产储量和矿产资源量的估计;公司预期的勘探、钻探、开发、建设及其他活动或成果;获得许可和监管批准的时间;EL转换为AMC的时间和获得情况;以及公司收入和资本支出的估计;预期的成本优势和运营框架;以及公司的其他未来计划、目标或预期。

前瞻性陈述或信息受多种已知和未知风险、不确定性及其他因素影响,这些因素可能导致实际事件或结果与前瞻性陈述或信息所反映的内容存在差异,包括但不限于与以下方面相关的风险:公共卫生危机对全球经济和社会的冲击;股票价格、债券价格、商品价格波动;资源、储量及矿化的计算;总体经济状况;外汇风险;利率风险;外国投资风险;关键人员流失;利益冲突;对管理层的依赖;未来所需融资的可用性和成本相关的不确定性;环境风险;运营和政治状况;玻利维亚和加拿大的监管环境;与社区关系和企业社会责任相关的风险;以及公司截至2025年6月30日止年度的年度信息表中“风险因素”标题下所述的其他因素及其其他公开申报文件。该清单并未穷尽可能影响公司任何前瞻性陈述或信息的因素。

前瞻性陈述必然基于管理层截至本新闻稿发布之日作出的若干估计、假设、信念、预期和意见,这些估计、假设、信念、预期和意见虽被管理层认为合理,但本质上受制于重大商业、经济和竞争方面的不确定性和或有事项。这些估计、假设、信念、预期和意见包括但不限于与公司开展当前和未来运营能力相关的估计、假设、信念、预期和意见,包括:公共卫生危机对我们运营和员工的影响;开发和勘探活动;此类运营的时间安排、范围、持续时间和经济可行性;估计、预测、预报、研究和评估的准确性和可靠性;公司实现或达成估计、预测和预报的能力;玻利维亚政治气候的稳定;公司获得并维持其矿产资产社会许可的能力;投入品的可获得性和成本;产出品的价格和市场;汇率;税率水平;及时获得必要批准或许可,包括玻利维亚多民族立法大会批准和核准与玻利维亚国家矿业公司(Corporación Minera de Bolivia)签订的采矿生产合同;公司玻利维亚合作伙伴将公司Carangas项目的Els  转换为AMC的能力;履行当前和未来义务的能力;在需要时以合理条件及时获得融资的能力;当前和未来的社会、经济和政治状况;以及与采矿业普遍相关的其他假设和因素。

尽管本新闻稿中包含的前瞻性陈述基于管理层认为合理的假设,但无法保证实际结果将与这些前瞻性陈述一致。本新闻稿中的所有前瞻性陈述均受这些警示性陈述的限制。因此,读者不应过度依赖此类陈述。除适用法律明确要求外,公司无义务且明确否认任何此类义务,无论是否因新信息、未来事件或其他原因而更新或更改前瞻性陈述,除非法律可能要求。这些前瞻性陈述截至本新闻稿发布之日作出。

致美国投资者的警示性说明

本新闻稿系依据加拿大现行证券法律的要求编制,该等要求与美国证券法律的要求存在差异。本文所含技术与科学信息系依据NI 43-101编制,该标准与美国证券交易委员会(“SEC”)所采用的标准存在差异。因此,本文所含技术与科学信息,包括任何矿产储量与矿产资源估算,可能无法与受SEC披露要求约束的美国公司所披露的类似信息进行比较。

有关公司的更多信息(包括 AIF)可在 SEDAR+ 上公司简介页面 www.sedarplus.ca、EDGAR www.sec.gov 以及公司网站 www.newpacificmetals.com 获取。

New Pacific Metals 公布更新后的 Carangas 初步经济评估结果:税后净现值(5%)26.5 亿美元,内部收益率 35.9%;产出 3.390 亿盎司银当量 一文首次出现在 New Pacific Metals Corp. 上。

Source: New Pacific Metals · 官方动态 · newpacificmetals.com

Licence: 负责人声明许可;来源异议或指示可逐项收紧

The original source is traceable; the Chinese content is written or translated with AI assistance ; check the original for details.