Minnova (TSXV: MCI; US-OTC: AGRDF) outlined a C$76.2-million ($53.4-million) plan to bring Manitoba’s PL gold mine back into production in 2028, using existing infrastructure to limit upfront spending.

The operation near Sherridon, roughly 630 km northwest of Winnipeg, would average 62,200 oz. annually over 10 years, according to a preliminary economic assessment (PEA) released Wednesday.

“This PEA confirms what we have believed about the PL gold mine: a high-grade open pit start, an existing mill and infrastructure and a modest capital requirement combine to deliver a short payback and strong returns,” President and CEO Gorden Glenn said in the release.

Starting with surface ore could help Minnova generate cash before relying entirely on underground mining. The approach recasts an earlier development plan that centred on underground production, giving the company a longer operating horizon to support its restart ambitions.

High grade

PL’s September resource estimate contains 3.76 million measured and indicated tonnes grading 4.98 grams gold per tonne for 601,158 ounces. Another 1.67 million inferred tonnes grade 3.78 grams for 202,810 ounces.

The open-pit portion includes 1.58 million measured and indicated tonnes grading 5.28 grams, containing 268,091 ounces. Lower reporting cut-off grades and changed mining constraints prevent a direct comparison with the historical resource estimate, Minnova says.

Minnova shares fell 3.2% to C15¢ by midday Thursday in Toronto, valuing the company at about C$19 million ($13 million). They’ve traded between 14¢ and 50¢ over the past year.

Cost exposure

At $3,000-per-oz. gold, the new assessment projects a $180.6-million after-tax net present value, discounted at 5%, and a 111% internal rate of return. Payback would take about eight months from production.

All-in sustaining costs are estimated at $2,288 per oz. A 20% gold-price decline to $2,400 cuts the after-tax value to $5 million. The open pits require moving about 21 tonnes of waste for every tonne of ore.

The company’s 2017 feasibility study envisaged a five-year operation producing about 46,500 oz. annually, mostly from underground mining. It estimated all-in sustaining costs of $942 per ounce.

That earlier study assumed gold at $1,250 per oz. and excluded inferred resources from its production plan. Different study standards, mining plans and price assumptions mean its returns aren’t directly comparable with the new assessment.

Minnova had already set out plans last month to expand its existing 1,000-tonne-per-day plant to 2,000 tonnes in the second operating year. That would allow higher output while surface mining supplies the mill, before the operation shifts underground.

Resource expansion

The update followed more than 13,500 metres of drilling in 131 holes between September last year and April, targeting resource expansion and improving confidence in the deposit, the company said in July.

The site, formerly known as Puffy Lake, operated from December 1987 to March 1989 before mining stopped, according to an environmental assessment filed with Manitoba.

Minnova plans further resource updates, metallurgical testing and work toward a prefeasibility study. Its existing environmental licence covers underground mining. The company’s development plans also call for amendments to accommodate open pits and new underground access.

来源:MINING.COM · mining.com

来源署名:MINING.COM

许可:负责人声明许可;来源异议或指示可逐项收紧

原始来源可追溯;中文内容由 AI 辅助生成或翻译,核对细节请看原文。

相关报道

代表稿正在阅读

Minnova 公布 7620 万加元重启曼尼托巴 PL 金矿计划

MINING.COM · 2026-10-16 07:24

Minnova(TSXV: MCI)公布初步经济评估,计划以 7620 万加元(5340 万美元)让曼尼托巴省 PL 金矿在 2028 年复产,利用现有基础设施控制前期投入。

最新进展正在阅读

Minnova 公布 7620 万加元重启曼尼托巴 PL 金矿计划

MINING.COM · 2026-10-16 07:24

Minnova(TSXV: MCI)公布初步经济评估,计划以 7620 万加元(5340 万美元)让曼尼托巴省 PL 金矿在 2028 年复产,利用现有基础设施控制前期投入。

内容有误?告诉我们

事件后续

查看完整事件

更多操作