MINING.COM· Cecilia Jamasmie·· 4 天前精选AI 评分78.0

智利国家铜业公司(Codelco)查出4.21万吨虚增铜产量

Codelco’s inflated copper output scandal hits 42,100 tonnes

本站公开

AI 导读

智利国家铜业公司(Codelco)董事长Bernardo Fontaine在股东特别会议上披露,公司查出4.21万吨被人为虚增的产量,另有一笔涉及1.7万吨铜库存、价值1.2亿至1.4亿美元的异常事项。公司已启动审计,并在三座矿山及总部解雇九名员工。Fontaine同时表示,过去八年投入320亿美元,年铜产量却从约160万吨降至120万吨,债务增加50%。

推荐理由

原文披露虚增产量与库存异常的具体吨数及问责进展,可据此了解这家铜企的治理与财务压力。

正文 · 原文

Chile’s state-owned copper giant Codelco has identified 42,100 tonnes of artificially inflated production in its reporting, exposing weaknesses in internal controls as the miner struggles with declining output, rising costs and mounting debt.

Board chairman Bernardo Fontaine disclosed the figure Thursday at an extraordinary shareholders’ meeting, adding that a separate irregularity had affected 17,000 tonnes of copper inventory valued at between $120 million and $140 million.

“Recent incidents related to production figures have affected confidence in Codelco and its reputation. There’s no point in denying it,” Fontaine said.

The revelations deepen concerns about Codelco’s turnaround after production fell to two-decade lows in 2022 and 2023. As one of the world’s largest copper producers, the company plays a critical role in global supply as demand grows from electrification, power grids, electric vehicles and AI data centres.

Codelco has ordered audits and dismissed nine employees across three mines and its corporate offices as it investigates whether production figures were overstated.

“This is a serious issue because it reveals weaknesses in control, traceability and operational validation,” Juan Carlos Guajardo, executive director of consultancy Plusmining, told MINING.COM.

Financial deterioration

Beyond the reporting scandal, Fontaine delivered a stark assessment of Codelco’s financial performance, revealing that billions of dollars in investment have failed to reverse declining production while costs and debt have climbed.

The company invested $32 billion over the past eight years, yet annual copper output fell from approximately 1.6 million tonnes to 1.2 million tonnes, Fontaine said.

Codelco accounting scandal claims eight more employees

Codelco transferred $7 billion to the Chilean government over the past four years, 43% less than in the preceding four-year period, despite a 30% increase in copper prices. The company also increased its debt by 50% to finance those contributions, he said.

Operating cash outflows rose 42%, while Codelco’s total cost per pound of copper in 2025 was 78% higher than that of a comparison group comprising three major multinational miners and Chile’s three largest mining operations.

Fontaine also criticized the performance of Codelco’s major development projects, saying they had failed to deliver the production and financial returns originally expected from the capital invested.

The figures highlight the challenge facing management as it attempts to restore profitability while maintaining the investments needed to sustain production.

Recovery strategy

Fontaine said the board and new management are developing a recovery plan focused on improving profitability, generating cash flow and strengthening the company’s long-term financial position.

The strategy will prioritize safety, profitability, operational and environmental sustainability, and stronger internal governance, including tighter controls, greater transparency and clearer accountability.

Codelco also plans to pursue growth through public-private partnerships while directing capital towards projects capable of generating stronger returns.

Chile copper mines disruptions put 5% of production at risk

“For too long, the discussion has been overly focused on how many tons Codelco produced, and that hasn’t been immune to generating false production figures. But we have to ask ourselves how much value each ton generates and how much return each dollar invested delivers,” Fontaine said.

The shift comes as Codelco expects copper production in 2026 to be closer to 1.2 million tonnes, with annual output projected at around 1.3 million tonnes over the following four years.

Fontaine acknowledged that restoring confidence would require stronger inventory audits, more effective oversight and greater individual accountability for operational decisions.

Codelco halts Andina mine as tailings spill threatens river

“There will be difficult times and the process will take time,” he said.

The recovery plan will test whether Codelco can translate its substantial capital spending into sustainable production and stronger financial returns while rebuilding trust in the figures used to measure its performance.

来源:MINING.COM · mining.com

许可:负责人声明许可;来源异议或指示可逐项收紧

原始来源可追溯;中文内容由 AI 辅助生成或翻译,核对细节请看原文。

相关报道

代表稿

智利国家铜业公司(Codelco)涉4.21万吨铜产量虚报

商务部驻智利经商处 · 经贸新闻 · 2026-11-07

智利国家铜业公司(Codelco)证实2024至2025年间存在产量虚报与重复计账,涉及铜产量4.21万吨,导致库存虚增1.7万吨,或需计提1.2亿至1.4亿美元会计减值,审计仍在进行,公司已解雇8名涉事高管。董事长方丹披露,近四年铜价上涨30%,公司上缴国库资金却下降43%(约70亿美元),债务增加50%。公司宣布新战略,摒弃唯产量论,聚焦安全、盈利与内控,并计划通过公私合营(PPP)寻求扩张。

最新进展

智利国家铜业公司(Codelco)涉4.21万吨铜产量虚报

商务部驻智利经商处 · 经贸新闻 · 2026-11-07

智利国家铜业公司(Codelco)证实2024至2025年间存在产量虚报与重复计账,涉及铜产量4.21万吨,导致库存虚增1.7万吨,或需计提1.2亿至1.4亿美元会计减值,审计仍在进行,公司已解雇8名涉事高管。董事长方丹披露,近四年铜价上涨30%,公司上缴国库资金却下降43%(约70亿美元),债务增加50%。公司宣布新战略,摒弃唯产量论,聚焦安全、盈利与内控,并计划通过公私合营(PPP)寻求扩张。

内容有误?告诉我们

文中公司资料

  • 智利国家铜业公司(Codelco)

    智利国有铜业巨头,承认报告中有4.21万吨铜产量被虚增,另有1.7万吨铜库存存在异常,并已解雇九名员工、启动审计。

    资料出处:原文依据

事件后续

查看完整事件