PLS 批准 19 亿澳元 P2000 项目,Pilgangoora 锂辉石产能目标约 200 万吨/年

PLS greenlights P2000 project as it aims for ~2 Mt/y of spodumene production capacity

本站公开

AI 导读

PLS 批准位于 Pilgangoora 的 19 亿澳元(13 亿美元)P2000 项目,这是公司历史上最大的投资决定。项目将新建 Jimmagunya 处理厂,把 Pilgangoora 锂辉石精矿年产能提升至约 200 万吨,首批产出预计在 2029 年 9 月季度。

推荐理由

PLS 批准 19 亿澳元 P2000 项目,可了解 Pilgangoora 锂辉石产能扩张的规模与时间表。

正文 · 原文

PLS says it has approved the A$1.9 billion ($1.3 billion) P2000 Project at Pilgangoora, marking the largest investment decision in the company’s history.

The project will increase Pilgangoora’s annual spodumene concentrate production capacity to approximately 2 Mt through construction of a new processing plant, Jimmagunya, with first production expected in the September quarter of 2029.

Building on the P680 and P1000 expansions, P2000 represents the next major phase of growth at Pilgangoora, PLS says.

The decision follows the completion of the P2000 Feasibility Study, which identified a more efficient approach to mining and processing the Pilgangoora orebody. Building on years of operating experience and technical studies, P2000 will enable more mineralised material to be recovered as ore, reducing waste movement and improving efficiency across the operation.

The new Jimmagunya processing plant will be built alongside the existing Pilgan plant, becoming the third major processing facility at Pilgangoora.

The project comprises a 9 Mt/y  dry plant, a 6.3 Mt/y wet plant, a tailings filtration facility and associated earthworks, services and infrastructure.

The project will enable approximately 67 Mt of mineralised material previously classified as waste to be economically recovered as ore, supporting higher future production rates and a larger ore reserve, PLS says.

Managing Director and CEO, Dale Henderson, said the decision marked a major milestone for PLS.

“P2000 will transform the scale and competitive position of PLS,” he said. “It provides a pathway to circa-2 Mt per annum of production, further extending PLS’ position as one of the world’s major lithium producers. The investment is expected to create significant long-term value for PLS and its stakeholders. With Pilgangoora 100% owned by PLS, this materially larger production base provides shareholders with substantial exposure to the additional value created in stronger lithium price environments.

“In a cyclical market, scale matters, but cost position matters more. P2000 delivers both with materially greater production at lower unit costs, strengthening Pilgangoora’s position on the global cost curve and creating a more resilient business through lithium market cycles.

“This next phase of growth builds on years of operating experience at Pilgangoora, our deepening knowledge of the orebody and advances in processing technology. The P2000 configuration is the next evolution, applying this experience to recover more of the orebody, reduce waste movement and lower the mine strip ratio.”

The project is expected to create more than 1,000 jobs during construction and around 500 ongoing operational roles, as well as procurement opportunities for Pilbara and Western Australian businesses.

As the project progresses, PLS says it will continue working closely with Traditional Owners, local communities, government and industry partners.

Early site preparation is underway, with construction expected to take approximately two and a half years. First production from Jimmagunya is targeted for the September quarter of 2029, followed by an approximately six-month ramp-up.

The post PLS greenlights P2000 project as it aims for ~2 Mt/y of spodumene production capacity appeared first on International Mining.

来源:International Mining · 矿业新闻 · im-mining.com

许可:负责人声明许可;来源异议或指示可逐项收紧

原始来源可追溯;中文内容由 AI 辅助生成或翻译,核对细节请看原文。

相关报道

代表稿正在阅读

PLS 批准 19 亿澳元 P2000 项目,Pilgangoora 锂辉石产能目标约 200 万吨/年

International Mining · 矿业新闻 · 2026-10-16 17:08

PLS 批准位于 Pilgangoora 的 19 亿澳元(13 亿美元)P2000 项目,这是公司历史上最大的投资决定。项目将新建 Jimmagunya 处理厂,把 Pilgangoora 锂辉石精矿年产能提升至约 200 万吨,首批产出预计在 2029 年 9 月季度。

最新进展

PLS 的 Pilgangoora 锂矿季度锂辉石精矿产量创 26.76 万吨纪录

Australian Mining · 行业资讯 · 2026-10-28 08:26

PLS 在西澳 Pilgangoora 项目 9 月季度锂辉石精矿产量达 267,600 吨,环比增长 25%,Ngungaju 选厂按计划于 7 月重启是主要支撑。当季单位运营成本下降 12% 至 539 澳元/吨,但精矿销量下降 11% 至 223,600 吨、平均实现售价下降 14% 至 1809 美元/吨,季度收入因此下降 24% 至 5.63 亿澳元。PLS 同期批准 P2000 扩建的 19 亿澳元最终投资决定,目标年产能约 200 万吨,预计 2029 年 9 月季度投产。