VANCOUVER, British Columbia –November 3, 2026 – Silvercorp Metals Inc. (“Silvercorp” or the “Company”) (TSX/NYSE American: SVM) announces an update for its budget and construction schedule for the construction of the El Domo Project (the “Project”).

The construction budget for the Project has been updated to $298.2 million, a net increase of $14.6 million compared to the $283.6 million estimate disclosed by the Company on February 4, 2026 (for reference, the 2021 Feasibility Study Budget was $248 million). The main items of increase or decrease are as follows:

  1. Diesel fuel adjustment: Ecuador eliminated diesel subsidies, resulting in, together with other factors, the diesel price increasing from under $3/gallon in December 2024 to $5.64/gallon in October 2026, an increase of $2.7/gallon. As a result, the fuel adjustment for Package #1 is $3.6 million and for Package #2 is $4.7 million, totaling $8.3 million for remaining construction.
  2. Enhancement work for Water Management Related Infrastructure: Due to heavy rainfall experienced at the Project, additional work to upgrade the designs and enhance the construction for reinforcement results in an increase of $3.5 million, plus site cleaning costs of $1.2 million, for a $4.7 million budget addition. This is added to the Package #1 TSF budget.
  3. Equipment and Facilities for Site Power Supply: $2.4 million increase mainly due to the additional demand for the power cables and power distribution facilities based on the detailed engineering design.
  4. Construction on Processing Plant: $3.7 million increase following execution of the Package #3 construction contract, reflecting further refinement of the quantities and unit rates in the contract bill of quantities.
  5. New Items:
    1. Two cofferdams and pipes beneath the TSF Starter Dam to drain the water from the impoundment area during the Construction Period, plus cemented roadside ditches are required to divert water from the construction site, at a cost of nearly $2 million. This is added to the Package #1 TSF budget.
    1. Two new Reactive Power Compensators (SVG)  are estimated at $2 million plus other power supply related items of $1.3 million, for a total increase of $3.3 million.
  6. Offsetting budget reductions of $9.8 million were mainly achieved through, among other things: (i) using rocks from the process plant site preparation for haul road construction instead of purchasing replacement materials for $1.8 million; (ii) eliminating the West Non-contact Water Channel for $1.5 million, as the explosives magazine site has effectively diverted surface water, (iii) reducing the permanent camp size for $0.7 million as the Construction Camp currently in use is satisfactory for long-term use, and (iv) reducing of contingency for $2.7 million. The reduction in contingency is not a direct cost saving, but a reduction in the Company’s allowance for future cost increases, of which $14.3 million remains.

Due to the extended rainfall experienced at site caused by Super El Nino, the El Domo completion date is currently expected to be delayed by four months. The Company is now targeting production at El Domo in November 2027, subject to, among other things, weather conditions, and contractor performance. There can be no assurance that production will commence when targeted.

Capital Cost Estimate Details:

The table below compares the Updated Budget to the Budget released on February 4, 2026, and also the Total Actual Expenditures as of September 30, 2026:

查看配图

Progress Achieved by September 30, 2026:

For Package #1: the main delay includes delays relating to TSF construction and Non-contact Water Channel. Site preparation for the process plant has been completed and construction of foundations for the processing plant is well underway.

查看配图

Package #2 – Open Pit Mining and Stripping

查看配图

The Company awarded the Mining Contract for the Package #2 Project to China Railway 19th Bureau Group Co., Ltd. (“CRCC 19”) on a “Unit Cost” basis, valued at $35 million for mining and stripping. This Updated Budget increases by $5.0 million, of which $4.7 million reflects the diesel price increase.

Package #3 – Processing Plant Construction and Equipment

查看配图

Foundations for the fine ore bin were 92% complete, 45% for the grinding & flotation plant, 21% for the thickener, 86% for the dewatering plant, 75% for the warehouse, and 35% for the oil depot. Buildings were 78% and 46% complete for the lab and office, respectively. The plant site is well protected by the Northeast Non-contact Water Channel.

As most costs are related to the pre-fabricated structural steel for the Process Plant which has been ordered and shipped from the factories, and payment is pending on arrival at Ecuador port and final installation, Total Actual Expenditures as of September 30, 2026 are not significant.

查看配图

Most equipment has been ordered and the Company has paid an approximate 30% down payment, which totals approximately $10.6 million.

Packages #4,5 -Site Infrastructure (bypass roads, powerline, standby diesel generators, water treatment plant)

查看配图

Construction of the Powerline has been delayed as more reviews and approvals have been required from CNEL. Only construction of a Substation at the El Domo site has commenced. Meanwhile, 10 gen-sets of 17 MW capacity have been manufactured and are ready to be shipped to site as an independent power supply. Continued delays in the construction of the Powerline would require that the Project rely on the gen-sets for longer, which may increase operating costs.

 About Silvercorp

Silvercorp is a Canadian mining company producing silver, gold, lead, and zinc with a long history of profitability and growth potential. The Company’s strategy is to create shareholder value by 1) focusing on generating free cash flow from long life mines; 2) organic growth through extensive drilling for discovery; 3) ongoing merger and acquisition efforts to unlock value; and 4) long term commitment to responsible mining and ESG. For more information, please visit our website at www.silvercorpmetals.com.

For further information

Silvercorp Metals Inc.

Lon Shaver

President

Phone: (604) 669-9397

Toll Free 1(888) 224-1881

Email: investor@silvercorp.ca

Website: www.silvercorpmetals.com

CAUTIONARY DISCLAIMER – FORWARD-LOOKING STATEMENTS

This news release includes “forward-looking statements” within the meaning of the United States Private Securities Litigation Reform Act of 1995 and “forward-looking information” within the meaning of applicable securities laws (collectively, “forward-looking information”) relating to, among other things statements regarding the recovery of the VAT as a tax credit, the construction schedule, duration, and costs for the development of the Project, the date which the Project is scheduled to be in production; the updated construction budget and its components; anticipated cost savings; diesel prices; timing of execution of mining contract and mobilization of personnel and equipment to the Project, timing of completion of detailed engineering design, delivery of diesel generators, and completion of the external powerline; reliance on gen-sets; and the funding of remaining construction costs. By their very nature, forward-looking information involves known and unknown risks, uncertainties and other factors that may cause our actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by the forward-looking information . Forward-looking information may in some cases be identified by words such as “will”, “anticipates”, “expects”, “intends” and similar expressions suggesting future events or future performance.

We caution that all forward-looking information is inherently subject to change and uncertainty and that actual results may differ materially from those expressed or implied by the forward-looking information. A number of risks, uncertainties and other factors, including but not limited to: fluctuating commodity prices; recent market events and condition; activities of anti-mining groups; estimation of mineral resources, mineral reserves and mineralization and metal recovery; interpretations and assumptions of mineral resource and mineral reserve estimates; exploration and development programs; climate change; severe weather, including flooding and extended rainfall; fuel and input cost increases, including as a result of changes to government subsidies or taxes; delays by third parties; construction risks and cost overruns; economic factors affecting the Company; timing, estimated amount, capital and operating expenditures and economic returns of future production; integration of future acquisitions into existing operations; permits and licences for mining and exploration in China; title to properties; non-controlling interest shareholders; acquisition of commercially mineable mineral rights; financing; competition; operations and political conditions; regulatory environment in Ecuador and China; regulatory environment and political climate in Bolivia and Ecuador; integration and operations of Adventus; environmental risks; natural disasters; dependence on management and key personnel; foreign exchange rate fluctuations; insurance; risks and hazards of mining operations; conflicts of interest; internal control over financial reporting as per the requirements of the Sarbanes-Oxley Act; outcome of current or future litigation or regulatory actions; bringing actions and enforcing judgments under U.S. securities laws; cyber-security risks; public health crises; the Company’s investment in New Pacific Metals Corp. and Auro Metals Inc.; and the other uncertainties, risks and other factors described in the Company’s Annual Information Form and other filings with Canadian and U.S. regulators on www.sedarplus.ca and www.sec.gov; could cause actual results and events to differ materially from those expressed or implied in the forward-looking information or could cause our current objectives, strategies and intentions to change. Accordingly, we warn investors to exercise caution when considering statements containing forward-looking information. We cannot guarantee that any forward-looking information will materialize and you are cautioned not to place undue reliance on this forward-looking information. Any forward-looking information contained in this news release represents expectations as of the date of this news release and is subject to change after such date. However, we are under no obligation (and we expressly disclaim any such obligation) to update or alter any statements containing forward-looking information, the factors or assumptions underlying them, whether as a result of new information, future events or otherwise, except as required by law. All of the forward-looking information in this news release is qualified by the cautionary statements herein.

A comprehensive discussion of other risks that impact Silvercorp can also be found in its public reports and filings which are available under its profile at www.sedarplus.ca. and on EDGAR at www.sec.gov.

来源:Silvercorp Metals · 官方动态 · silvercorpmetals.com

许可:负责人声明许可;来源异议或指示可逐项收紧

原始来源可追溯;中文内容由 AI 辅助生成或翻译,核对细节请看原文。

相关报道

代表稿当事方或官方发布正在阅读

Silvercorp 将厄瓜多尔 El Domo 项目建设预算上调至 2.982 亿美元

Silvercorp Metals · 官方动态 · 2026-11-04

Silvercorp 将厄瓜多尔 El Domo 项目建设预算上调至 2.982 亿美元,较 2026 年 2 月 4 日披露的 2.836 亿美元净增 1460 万美元。柴油补贴取消推高燃油成本,使 Package #1 和 Package #2 合计增加 830 万美元;因强降雨,尾矿库与供水设施加固等也增加了支出。受超强厄尔尼诺带来的持续降雨影响,项目完工推迟四个月,公司目前目标是在 2027 年 11 月投产。

最新进展当事方或官方发布正在阅读

Silvercorp 将厄瓜多尔 El Domo 项目建设预算上调至 2.982 亿美元

Silvercorp Metals · 官方动态 · 2026-11-04

Silvercorp 将厄瓜多尔 El Domo 项目建设预算上调至 2.982 亿美元,较 2026 年 2 月 4 日披露的 2.836 亿美元净增 1460 万美元。柴油补贴取消推高燃油成本,使 Package #1 和 Package #2 合计增加 830 万美元;因强降雨,尾矿库与供水设施加固等也增加了支出。受超强厄尔尼诺带来的持续降雨影响,项目完工推迟四个月,公司目前目标是在 2027 年 11 月投产。

内容有误?告诉我们

事件后续

查看完整事件

更多操作