Boroo 以最高 1.4 亿加元收购 Victoria Gold 的 Eagle 金矿

Boroo signs $100M deal for Yukon Eagle gold mine

本站公开

来源署名:MINING.COM

AI 导读

私人企业 Boroo 同意以最高 1.4 亿加元(约 1 亿美元)收购 Victoria Gold,从而推进 Eagle 金矿的修复与潜在复产;该矿在 2024 年 6 月发生堆浸场溃塌后停产。交易包括 4000 万加元首付款和最高 1 亿加元的许可与商业生产里程碑付款,由 Gatsuurt Mining 成为 Victoria 唯一股东,尚需安大略高等法院批准,目标在 12 月 31 日前后交割。Boroo 计划 2027 至 2029 年投入约 8 亿加元用于修复、水处理、场地稳定和分阶段复产,并表示将与 Na-Cho Nyäk Dun 原住民继续磋商。

推荐理由

交易把收购对价、分期里程碑与后续复产支出放在一起,可据此了解尾矿库事故后矿山易手的责任安排。

正文 · 原文

Private entity Boroo has agreed to acquire Victoria Gold for up to C$140 million (about $100 million), advancing plans to potentially rehabilitate and restart its Eagle gold mine more than two years after a heap-leach collapse shut the Yukon operation.

The Singapore-based buyer would pay C$40 million upfront and another C$100 million as permitting and commercial-production milestones are met, it said in a release Thursday. Eagle lies about 375 km north of Whitehorse, in the traditional territory of the First Nation of Na-Cho Nyäk Dun.

“Our agreement to acquire Victoria Gold and the Eagle gold mine marks a pivotal turning point for this foundational Yukon asset,” Boroo CEO Dulguun Erdenebaatar said in a statement. “Over the past year, our technical and environmental teams have spent countless hours on the ground conducting rigorous due diligence to ensure that the Eagle mine can be restarted responsibly and that the site’s environmental challenges are addressed.”

Discussions with the Na-Cho Nyäk Dun remain ongoing, the company said.

The agreement offers a route out of receivership for Victoria following the June 2024 failure, which released contaminated material beyond the mine’s containment system. Court approval is still required, and the proposed purchase leaves important questions about the division of cleanup liabilities and recovery of public funds.

Restart spending

Boroo expects to spend about C$800 million between 2027 and 2029 on rehabilitation, water treatment, site stabilization and a phased restart. It anticipates spending more than C$600 million over the initial mine life to support and extend operations.

Those plans, together with the purchase price, underpin its announced commitment of more than C$1.5 billion into Canada. The company didn’t disclose a firm production restart date or identify financing committed specifically to Eagle.

Wholly owned subsidiary Gatsuurt Mining would become Victoria’s sole shareholder. Receiver PricewaterhouseCoopers intends to seek approval from the Ontario Superior Court of Justice in early December, targeting closing around Dec. 31.

Boroo said it would assume certain remediation obligations and provide financial security to Yukon at closing. Under the proposed court order, some existing liabilities would remain with Victoria while others would transfer to a separate company that stays in receivership. The announcement didn’t disclose the amount of security.

Boroo said it had settled terms of a framework agreement with Yukon authorities covering remediation, restart and closure, effective when the acquisition closes.

Mongolian ownership

Boroo is privately held and ultimately controlled by Mongolian investor Tulga Erdenebileg, according to its June financial statements. A May 2025 takeover filing disclosed that he owned 70% through TDB Capital Singapore and Eminent Stride, with ABC Trading holding 20% and CEO Erdenebaatar 10%.

Erdenebileg also indirectly owns 29.69% of Mongolia’s Trade and Development Bank, according to the bank’s investor disclosures.

Boroo acquired Barrick’s Lagunas Norte gold mine in Peru in 2021 and controls Steppe Gold (TSX: STGO). A February filing put its Steppe interest at 56.88%.

June accounts for Boroo and a defined group of subsidiaries reported $498.8 million in cash, $391.7 million in borrowings and a further $107.2 million in bonds payable to related group companies. These accounts don’t fully consolidate all Boroo subsidiaries.

The group raised $300 million through a 9.5% bond issue last year. Its annual outlook also outlined about $390 million of spending in 2026–27, principally for a processing expansion at Lagunas Norte.

Cleanup legacy

An independent review attributed Eagle’s June 24, 2024 failure to static liquefaction, in which material loses strength and flows. It identified poorly draining ore, accumulated water, irrigation and slope conditions as contributing factors. About 1.8 million tonnes escaped containment.

PwC became receiver on Aug. 14, 2024, following Yukon’s application. Boroo entered exclusive acquisition talks in April this year.

Yukon has authorized loans of up to C$220 million to the receiver, secured by a priority claim over other creditors. That ceiling doesn’t represent the amount ultimately spent or recovered.

Boroo’s initial work would focus on stabilizing the failed heap and treating cyanide-impacted water. Its proposed restart also includes reviewing pit and waste-rock stability, validating reserves and resources, repairing equipment and introducing tighter controls over ore characteristics and blending.

来源:MINING.COM · mining.com

来源署名:MINING.COM

许可:负责人声明许可;来源异议或指示可逐项收紧

原始来源可追溯;中文内容由 AI 辅助生成或翻译,核对细节请看原文。

相关报道

代表稿正在阅读

Boroo 以最高 1.4 亿加元收购 Victoria Gold 的 Eagle 金矿

MINING.COM · 2026-10-23 06:06

私人企业 Boroo 同意以最高 1.4 亿加元(约 1 亿美元)收购 Victoria Gold,从而推进 Eagle 金矿的修复与潜在复产;该矿在 2024 年 6 月发生堆浸场溃塌后停产。交易包括 4000 万加元首付款和最高 1 亿加元的许可与商业生产里程碑付款,由 Gatsuurt Mining 成为 Victoria 唯一股东,尚需安大略高等法院批准,目标在 12 月 31 日前后交割。Boroo 计划 2027 至 2029 年投入约 8 亿加元用于修复、水处理、场地稳定和分阶段复产,并表示将与 Na-Cho Nyäk Dun 原住民继续磋商。

最新进展正在阅读

Boroo 以最高 1.4 亿加元收购 Victoria Gold 的 Eagle 金矿

MINING.COM · 2026-10-23 06:06

私人企业 Boroo 同意以最高 1.4 亿加元(约 1 亿美元)收购 Victoria Gold,从而推进 Eagle 金矿的修复与潜在复产;该矿在 2024 年 6 月发生堆浸场溃塌后停产。交易包括 4000 万加元首付款和最高 1 亿加元的许可与商业生产里程碑付款,由 Gatsuurt Mining 成为 Victoria 唯一股东,尚需安大略高等法院批准,目标在 12 月 31 日前后交割。Boroo 计划 2027 至 2029 年投入约 8 亿加元用于修复、水处理、场地稳定和分阶段复产,并表示将与 Na-Cho Nyäk Dun 原住民继续磋商。

内容有误?告诉我们

文中公司资料

  • 巴里克(Barrick)

    Boroo于2021年收购了巴里克位于秘鲁的Lagunas Norte金矿。

    资料出处:原文依据

事件后续

查看完整事件