Hudbay与三菱批准美国亚利桑那州Copper World铜矿开发

Hudbay, Mitsubishi greenlight Copper World project development in Arizona

Public on this site

AI summary

Hudbay与三菱批准开发美国亚利桑那州Copper World铜矿项目,Hudbay持股70%、三菱持股30%,预计2029年下半年首次产出。最终可行性研究显示,前10年年产铜10.2万吨,较2023年预可行性研究的9.2万吨提高11%;基础方案基于3.90亿吨、品位0.47% Cu的储量,矿山寿命15年,仅需州和地方许可。扩建方案拟将矿山寿命延长至37年,第10年扩展至联邦土地并需取得联邦许可,第11至20年年产铜11.7万吨。

Why it matters

原文列出Copper World的储量、产能爬坡与两阶段许可路径,可据此了解项目开发节奏。

Hudbay Minerals Inc and its partner Mitsubishi Corporation have approved the development of what they say will be one of the largest open-pit copper mines in the US.

The news came when announcing the results of the definitive feasibility study and related prefeasibility studies (collectively referred to as ‘the DFS’) for the Copper World project, 70% owned by Hudbay and 30% owned by Mitsubishi.

With first production projected in the second half of 2029, Copper World will be the first of the next generation of long-life, low-cost copper mines in the Americas, Hudbay claims.

The DFS outlines annual copper production of 102,000 t over the first 10 years, an 11% increase when compared to 92,000 t in Hudbay’s 2023 prefeasibility study for Copper World. This could see Hudbay’s consolidated annual copper production increase to approximately 250,000 t, doubling current production levels, with other brownfield growth projects underway.

The base case for Copper World contemplates a 15-year mine life utilising mineral reserves (390 Mt at 0.47% Cu), and requires only state and local permits,

This base case further optimises the 2023 PFS mine plan with an in-pit crushing and conveying (IPCC) system in year four and an expansion of the concentrator from 54,431 t/d to 81,64t t/d in year five. Concentrator expansion enables a 43% increase in average annual copper production to 120,000 t in years six to 10 compared with 84,000 t over the first five years.

The addition of an IPCC system, starting in year four, is predicated on efficiently managing the higher mined material tonnages to match the concentrator expansion throughput in year five. The IPCC system will have a nominal design capacity of 90,718 t/d and forms a critical component of the mine plan that will convey ore from the East pit to stockpiles and the processing plant. The IPCC will enable fewer haul trucks and lower emissions and operating costs, Hudbay added.

The extension case for the Copper World project contemplates a 37-year mine life utilising only measured and indicated mineral resources and expands mining activities onto federal lands in year 10, subject to obtaining federal permits, maintaining annual copper production of 117,000 t from years 11 to 20.

The fully permitted concentrate leach facility – which would produce “Made in America” copper cathode for the US critical minerals supply chain – represents a key future upside opportunity.

“The approval of the development of Copper World represents a significant milestone for Hudbay, our partners at Mitsubishi, our stakeholders, and the copper landscape in the US,” Peter Kukielski, Hudbay’s Chief Executive Officer, said. “Copper World is one of the most attractive copper growth projects in the Americas, offering some of the highest copper grades, lowest cash costs and favourable capital intensity.”

The Copper World project includes four deposits discovered in 2021, together with the East deposit. Copper World is planned to be a traditional open-pit shovel and truck operation with a conventional flotation concentrator producing copper concentrate and molybdenum concentrate. A new resource model was completed for the 2022 PEA, which contemplated a two-phased mine plan with Phase I as a standalone operation requiring state and local permits only and Phase II expanding onto federal lands requiring federal permits. Phase I contemplated a 54,431 t/d sulphide concentrator and Phase II assumed an expansion of the concentrator to 81,64t t/d.

The post Hudbay, Mitsubishi greenlight Copper World project development in Arizona appeared first on International Mining.

Source: International Mining · 矿业新闻 · im-mining.com

Licence: 负责人声明许可;来源异议或指示可逐项收紧

The original source is traceable; the Chinese content is written or translated with AI assistance ; check the original for details.

Related coverage

Representative report

Hudbay 与三菱批准美国 Copper World 铜矿项目建设

Revista ProActivo · 行业资讯 · 2026-10-22 02:39

Hudbay 与三菱已正式作出最终投资决定,推进位于美国亚利桑那州、距 Tucson 东南约 50 公里的 Copper World 铜矿项目建设,预计 2029 年下半年投产。Hudbay 持股 70%、三菱持股 30%;最终可行性研究预计前 10 年年均产铜 102,000 吨,较 2023 年预可行性研究的 92,000 吨提高 11%,前 10 年平均 C1 现金成本为 1.65 美元/磅。初始增长资本估计为 20.70 亿美元,扣除贵金属产品流协议预付款后为 18.40 亿美元;融资包括三菱 6 亿美元初始股权投资、Wheaton Precious Metals 2.30 亿美元预付款及约 6.50 亿美元项目级债务融资。项目证实及可信储量 3.90 亿吨、铜品位 0.47%,选矿厂初始处理能力 60,000 吨/日,计划第五年扩至 90,000 吨/日。

Latest

Hudbay 与三菱批准美国 Copper World 铜矿项目建设

Revista ProActivo · 行业资讯 · 2026-10-22 02:39

Hudbay 与三菱已正式作出最终投资决定,推进位于美国亚利桑那州、距 Tucson 东南约 50 公里的 Copper World 铜矿项目建设,预计 2029 年下半年投产。Hudbay 持股 70%、三菱持股 30%;最终可行性研究预计前 10 年年均产铜 102,000 吨,较 2023 年预可行性研究的 92,000 吨提高 11%,前 10 年平均 C1 现金成本为 1.65 美元/磅。初始增长资本估计为 20.70 亿美元,扣除贵金属产品流协议预付款后为 18.40 亿美元;融资包括三菱 6 亿美元初始股权投资、Wheaton Precious Metals 2.30 亿美元预付款及约 6.50 亿美元项目级债务融资。项目证实及可信储量 3.90 亿吨、铜品位 0.47%,选矿厂初始处理能力 60,000 吨/日,计划第五年扩至 90,000 吨/日。

Something wrong? Tell us

Event follow-ups

See the full event

More actions