自由港麦克莫兰(Freeport-McMoRan)将 2026 年合并铜销售预期下调至 30 亿磅、2027 年下调至 37 亿磅,分别低于 7 月预测的 31 亿磅和 38 亿磅,2028 年 41 亿磅的预估维持不变。首席财务官 Maree Robertson 将 2026 年的下调归因于美国与智利产量略降,2027 年的下调则源于矿山计划更新;美国受极端天气影响开工率与生产率,智利 El Abra 因边坡管理限制高品位矿石开采,秘鲁 Cerro Verde 表现高于预期。Grasberg 在 2025 年 9 月泥石流后分阶段复产,第三季度 Grasberg Block Cave 采矿速率约 7 万吨/日,高于第二季度的 5.3 万吨,公司预计 2027 年中期达到 80% 产能、年底接近满产。第三季度单位净现金成本升至 2.07 美元/磅,上年同期为 1.40 美元/磅。

Text · original

The Chinese translation is being made; the original is shown for now.

查看配图
Freeport's Grasberg operation. Credit: Freeport McMoRan via YouTube.

Freeport-McMoRan (NYSE: FCX) cut its copper sales forecasts for this year and next while reaffirming the recovery timetable for its Grasberg operation in Indonesia.

Consolidated copper sales are projected to hit 3 billion lb. in 2026 and 3.7 billion lb. next year, Freeport said Tuesday in a statement. Those compare with 3.1 billion lb. and 3.8 billion lb., respectively, in a July forecast. The 2028 estimate remains 4.1 billion pounds.

Chief financial officer Maree Robertson attributed the 2026 reduction to slightly lower U.S. and Chilean production and the 2027 revision to updated mine plans, according to a transcript of the company’s quarterly analyst call.

Extreme weather reduced U.S. operating rates and productivity, while slope management restricted access to higher-grade ore at Chile’s El Abra mine, Freeport’s presentation showed. Cerro Verde in Peru performed above forecast.

Higher profit

Robertson made the comments after Freeport reported net income attributable to common shareholders of $1.17 billion (C$1.64 billion) in the third quarter, or 81¢ a diluted share, compared with $674 million, or 46¢, a year earlier. Revenue increased 8% to $7.55 billion, Freeport said in its release.

Adjusted earnings, a non-GAAP measure, were $1.28 billion, or a higher-than-expected 88¢ a share, after excluding $101 million in net charges. Operating cash flow rose to $1.98 billion from $1.69 billion.

The financial gains came despite copper sales falling to 749 million lb. from 977 million lb. a year earlier. Freeport’s realized copper price rose to $6.54 a lb. from $4.68. Quarterly copper production was 832 million lb., with inventories accounting for much of the gap between production and sales.

Freeport still expects about 100 million lb. of copper to remain in Indonesian smelter inventory at year-end. That deferral was already included in July’s outlook and is separate from the newly announced reductions.

Restart progress

Grasberg’s phased restart following a deadly September 2025 mudslide at the mine remains central to the projected rebound in output. Freeport expects the Indonesian operation to reach 80% of capacity by mid-2027 and approach full capacity by year-end.

Mining rates at the Grasberg Block Cave averaged about 70,000 tonnes a day in the third quarter, up from 53,000 tonnes in the second.

Material-handling upgrades remain on schedule for completion early next year, while preparations for restarting Production Block 1S are advancing toward mid-2027. Dry weather has helped mining but limited water availability has complicated efforts to raise milling rates, with the impact so far limited, Freeport said.

Grasberg’s restart is “progressing well,” BMO Capital Markets mining analyst Katja Jancic said Tuesday in a note. “Overall, we view the Grasberg ramp-up as increasingly de-risked.”

Rising costs

Cost pressures persist. Third-quarter unit net cash costs were $2.07 per lb. of copper, against $1.40 a year earlier, after by-product credits and excluding idle-facility, direct recovery and restoration costs. Freeport recorded $244 million of those excluded costs during the quarter.

Capital spending is now expected to hit $4.4 billion this year and $5.2 billion next year, compared with $4.3 billion and $4.8 billion in July. The 2027 increase mainly reflects additional U.S. mining equipment and inflation, Robertson said.

A decision on expanding Arizona’s Bagdad mine is expected this quarter, Freeport also said. Capital costs for a new concentrator, mining equipment and expanded infrastructure could reach about $4.5 billion, according to the company.

The expansion could add 200 million to 250 million lb. of copper annually. It would take three to four years to complete, Freeport said.

Source: Canadian Mining Journal · 行业资讯 · canadianminingjournal.com

Licence: 负责人声明许可;来源异议或指示可逐项收紧

The original source is traceable; the Chinese content is written or translated with AI assistance ; check the original for details.

Related coverage

Representative reportReading now

自由港下调铜销售预期,Grasberg 复产推进

Canadian Mining Journal · 行业资讯 · 2026-10-28 22:18

自由港麦克莫兰(Freeport-McMoRan)将 2026 年合并铜销售预期下调至 30 亿磅、2027 年下调至 37 亿磅,分别低于 7 月预测的 31 亿磅和 38 亿磅,2028 年 41 亿磅的预估维持不变。首席财务官 Maree Robertson 将 2026 年的下调归因于美国与智利产量略降,2027 年的下调则源于矿山计划更新;美国受极端天气影响开工率与生产率,智利 El Abra 因边坡管理限制高品位矿石开采,秘鲁 Cerro Verde 表现高于预期。Grasberg 在 2025 年 9 月泥石流后分阶段复产,第三季度 Grasberg Block Cave 采矿速率约 7 万吨/日,高于第二季度的 5.3 万吨,公司预计 2027 年中期达到 80% 产能、年底接近满产。第三季度单位净现金成本升至 2.07 美元/磅,上年同期为 1.40 美元/磅。

LatestReading now

自由港下调铜销售预期,Grasberg 复产推进

Canadian Mining Journal · 行业资讯 · 2026-10-28 22:18

自由港麦克莫兰(Freeport-McMoRan)将 2026 年合并铜销售预期下调至 30 亿磅、2027 年下调至 37 亿磅,分别低于 7 月预测的 31 亿磅和 38 亿磅,2028 年 41 亿磅的预估维持不变。首席财务官 Maree Robertson 将 2026 年的下调归因于美国与智利产量略降,2027 年的下调则源于矿山计划更新;美国受极端天气影响开工率与生产率,智利 El Abra 因边坡管理限制高品位矿石开采,秘鲁 Cerro Verde 表现高于预期。Grasberg 在 2025 年 9 月泥石流后分阶段复产,第三季度 Grasberg Block Cave 采矿速率约 7 万吨/日,高于第二季度的 5.3 万吨,公司预计 2027 年中期达到 80% 产能、年底接近满产。第三季度单位净现金成本升至 2.07 美元/磅,上年同期为 1.40 美元/磅。

Something wrong? Tell us

Companies in this article

  • 自由港麦克莫兰 (Freeport-McMoRan)

    美国矿业公司,运营印尼Grasberg铜金矿,并公布季度业绩与铜销售指引。

    Source of the data: 原文依据

Event follow-ups

See the full event

More actions